论文部分内容阅读
(一) 概况刘家浪水电站座落在洮河中上游,设计水头17m,设计流量4×16m~3/S,总装机容量4×2000kW。采用ZD560-LH-180型轴流定浆式水轮机和TSL260/35-20型发电机,配用CT-40型机械液压式调速器。刘家浪水电站是孤立运行的水电站,机组安装
(I) General Liujialang Hydropower Station is located in the middle and upper reaches of Bahe River. It has a design head of 17m and a design flow of 4 × 16m 3 / S with a total installed capacity of 4 × 2000kW. Adopt ZD560-LH-180 type axial flow setting turbine and TSL260 / 35-20 type generator, equipped with CT-40 type mechanical hydraulic governor. Liujialang Hydropower Station is isolated operation of hydropower stations, unit installation