白溪水库工程是以供水、防洪为主兼发电、灌溉的大型水利枢纽工程,其中混凝土面板堆石坝最大坝高达124.4 m,坝长398 m,坝体填筑总量达400万m+3,工程于1996年12月31日开工,2001年3月31日完工。在施工中由于垫层料变化很大,主要是设计配合比变更、干密度提高、各档级配料的调整、轧制流程不同,运输距离加长等原因,投标中标价为20.02元/m+3,而实际施工成本价达54.23元/m+3,从而引起甲乙双方争议。
Baixi Reservoir Project is a large-scale water control project mainly involving water supply, flood control and power generation and irrigation. The maximum dam height of concrete faced rockfill dam is 124.4 m and the dam length is 398 m. The total dam filling volume is 4 million m +3, the project started on December 31, 1996 and completed on March 31, 2001. In the construction of the cushion material changes greatly, mainly the design mix changes, dry density increased, the various grades of ingredients adjustment, the rolling process is different, longer transport distance and other reasons, the tender price of 20.02 yuan / m +3, while the actual construction cost price of 54.23 yuan / m +3, resulting in controversy between the two sides.