2016年,泸天化公司装置运行整体良好,创造了合成新老系统超400天的长周期历史记录,2套煤锅炉已创造了超200天的长周期优异成绩,全年设备长周期个数为16个。但从全年各装置的设备状态和缺陷统计上分析,设备管理还应持续升华,并应对问题突出点进行跟踪管理,制定和落实切实的技术措施,为2017年的装置长周期、稳定、高效运行奠定良好的基础。本文从2016年各装置的缺陷统计出发,结合装置状态和缺陷分析,拟订了2017年设备的管理重点。
In 2016, Lutianhua’s plant operation was in good condition as a whole, creating a long-period history record of more than 400 days for the synthesis of old and new systems. 2 sets of coal-fired boilers have achieved excellent results in over 200 days of long cycles. The number of long-term equipment throughout the year 16. However, from the statistic analysis of the equipment status and defects of all the equipments in the whole year, the equipment management should continue to sublimate, and follow-up management should be made to highlight the problems so as to formulate and implement practical technical measures to stabilize and prolong the plant’s long cycle in 2017 Run to lay a good foundation. In this paper, starting from the defect statistics of each device in 2016, the key points of the management of the device in 2017 are formulated based on the analysis of device status and defects.