金田水电站砌石支墩坝,是根据硬壳坝及拱坝的原理建造的砌石轻型坝。在河谷较宽的条件下,适合于修建这种形式的坝。该坝于1970年开始施工,1975年建成投产。水库区集雨面积240平方公里,坝高53米,坝后电站装机容量5,800千瓦,计划利用尾水灌溉农田13万亩。大坝全长245米,除溢流坝及两岸边为重力坝外,其余155米均为砌石支墩坝,由13个支墩和12个跨梁组成,经四年多运行,情况良好。
Jinda hydropower station masonry pier is based on the principle of hard-shell dam and arch dam construction light stone dam. In the wider valley conditions, suitable for the construction of this form of dam. The dam started construction in 1970 and was put into operation in 1975. Reservoir area rainwater catchment area of 240 square kilometers, dam height of 53 meters, post-dam power station installed capacity of 5,800 kilowatts, plans to use tailwater irrigation 13 acres of farmland. The total length of the dam is 245 meters. Except for the overflow dam and the gravity dam on both sides of the bank, the remaining 155 meters are masonry pier with 13 support piers and 12 span beams. After more than four years of operation, the dam is in good condition .