网络计划技术,就是用网络图的形式,表示出一项工程计划中的各个作业(活动,任务、工序)的先后顺序及相互关系,通过计算找出工程计划中的关键作业和关键路线,最合理地使用人力、物力、资金、空间(统称为资源),多快好省地完成任务。长期以来,企业在安排生产和施工进度计划时,都习惯于采用横道图(即工程进度表)。它虽然简单明了,容易理解,容易绘制,容易应用,但存在下述缺点:各个作业(工序)之间的相互依赖关系、相互制约关系,不能一览无余地看出来,因而对某个作业(工序)的提前或推迟所造成的影响无法直接看出;从时间进度上说来,哪些是关键作业,哪些是非关键作业,图上不能标出;不同的安排方案,无法比较其优劣程度;一个项目如果包括几百甚至上千个作业,用横道图很难表示出来;如果施
Network planning technology is to use the form of a network diagram to show the sequence and relationship of various operations (activities, tasks, processes) in a project plan, and to find out the key operations and key routes in the project plan by calculation. Rationally use manpower, material resources, funds, and space (collectively referred to as resources) to complete tasks quickly and efficiently. For a long time, companies have been accustomed to adopting crossbar diagrams (ie, project schedules) when arranging production and construction schedules. Although it is simple and straightforward, easy to understand, easy to draw, and easy to apply, it has the following disadvantages: The interdependence and mutual restraint relationship between various operations (processes) cannot be seen in a glance. Therefore, an operation (process) The impact of the advance or delay can’t be seen directly; from the time schedule, what are the key operations and what are the non-key operations, which can not be marked on the map; different arrangements can not compare the strengths and weaknesses; If the project includes hundreds or even thousands of jobs, it is difficult to represent it with a bar chart;