水利水电工程尾工的合同管理

来源 :水利水电工程造价 | 被引量 : 0次 | 上传用户:fht5403
下载到本地 , 更方便阅读
声明 : 本文档内容版权归属内容提供方 , 如果您对本文有版权争议 , 可与客服联系进行内容授权或下架
论文部分内容阅读
水利水电工程尾工阶段是指主要建筑物已施工完毕,施工人员、设备也已撤离施工现场,但还处于工程的质保期的阶段。在这个阶段合同的工程款的结算、竣工决算、索赔等尚未处理完毕,现场尚未移交。在这个阶段问题处理的好,一般都会使企业受益很多,如会给企业增加利润,会使企业的信誉提高,会使企业内部管理制度进一步完善等。作为承包商一定要对尾工工程的合同管理予以加强和重视。 Water conservancy and hydropower projects at the end of the stage refers to the main building has been completed, construction workers, equipment has evacuated the construction site, but still in the project’s warranty period. At this stage, the contract settlement, completion and settlement of accounts, claims, etc. have not yet been completed and the site has not yet been transferred. At this stage the problem is handled well, and generally will benefit a lot of enterprises, such as increasing profits for the enterprise, will increase the credibility of enterprises, will enable enterprises to further improve the internal management system. As a contractor must be on the end of the project contract management to be strengthened and attention.