论文部分内容阅读
摘要:伴随社会的发展,科技进步,城市建设的多元化。很多高层建筑向多功能、多用途方向发展,在工程设计和施工实践中,梁式转换层得到了广泛的采用和认可;目前在国内外一些已建成的带转换层的高层建筑中,钢筋混凝土梁式转换层占70%以上,它实现了上下建筑空间和结构形式的变化。
关键词:高层建筑 钢筋混凝土 梁式转换层 钢筋连接
Abstract: with the development of society, the progress of science and technology, diversification of city construction. Many high-rise buildings to the development of multi-function, multi-purpose direction, in the design and construction practice, girder transfer floor has been widely used and recognized at home and abroad; some have been built with the conversion layer of high-rise building conversion layer, reinforced concrete beam accounted for more than 70%, it realizes the change of architectural space upper and lower structure.
Key words: high-rise buildings of reinforced concrete girder transfer floor reinforcement connection
中图分类号: [TU208.3] 文献标识码:A 文章编号:2095-2104(2013)
一、钢筋安装顺序
高层建筑梁式转换层钢筋用量大、型号多;转换梁截面大,梁上下钢筋布置错综复杂。准确放样与下料、合理安排好钢筋就位次序尤为重要。放样时考虑好钢筋之间的穿插避让关系,确定制作尺寸和绑扎顺序,钢筋工程安装顺序如下.
搭钢管支架—分层排布主梁上部纵筋、套箍筋—梁上部主筋与箍筋绑扎牢固—拆支架横杆—洞口加固筋就位—穿梁下部主筋和腰筋、垫好梁下保护层短筋—下部主筋与箍筋绑扎牢固—铺放板底双向双层钢筋—逐层向上铺设暗梁处的中间部位腰筋—上下水电气管线敷设、钢筋马凳的焊接固定—铺放及绑扎板上部钢筋及表面加强筋。
二、转换层钢筋的连接与安装
(一)鋼筋翻样与下料
转换大梁的含钢量大,主筋长,布置密,在两梁相交的柱节点区上下共有几十层上百根主筋在此“相聚”,加上腰筋、柱筋等,主筋还须弯起锚固,众筋“抢位”现象十分突出。任何一根主筋的就位错误,均会造成大量的返工。因此,准确地翻样和下料是钢筋顺利施工的前提。
(1)钢筋翻样前必须弄清设计意图;审核、熟悉设计文件及有关说明;掌握
现行规范的有关规定。翻样时要结合实际并考虑方便施工。
(2)一般设计设计转换大梁的主筋在柱节点区均弯起锚固,施工难度大。可与设计单位协商解决,如:大梁的最上一排面筋向下弯并锚固至底筋以上;底筋的最下一排主筋尽量靠柱边上弯25d,其余主筋全部取销弯锚,负筋亦不起弯,均伸至弯起筋即可(柱截面大,锚固长度满足要求)。这样一来,增大了节点空间,为混凝土的灌注和振捣提供了条件。
(3)梁上部的主筋接头要求设置在跨中1/3跨长内,下部主筋接头要求设在靠近支座1/3跨长内。由于梁内主筋多,主筋下料时,必须考虑并调整好每根钢筋的接头位置,以保证主筋的焊接接头相互错开并满足现行规范要求。
(4)为方便钢筋的安装就位,满足上述规范要求,必须对所有梁主筋按就位顺序进行编号。
(5)梁箍筋大,下料时要注意对焊接头位置,避免接头出现在箍筋的弯折处。
(二)各部位钢筋连接方式
转换层中钢筋的种类繁多,不同位置钢筋受力情况也不尽相同,因此,各部位应综合受力情况、施工难度、经济效益等采用不同的连接方式。
(1)转换层大梁的主筋是转换层中最重要的受力单元,应采用最可靠且对钢 筋无损害的连接方式,通常采用冷挤压连接法。
(2)转换层柱钢筋、剪力墙竖向分布筋宜采用电渣压力焊。
(3)转换层主梁腰筋及箍筋、联系梁主筋、板钢筋一般采用闪光焊接。
(4)其他受力较次要部位,如联系梁架力筋及箍筋可采用绑扎连接。
(三)钢筋支撑架的搭设
在钢筋成型及绑扎施工过程中,由于钢筋特长,只能在施工现场进行连接,在连接时,必须搭设钢筋支撑架,支撑架的搭设是便于钢筋绑扎的关键。
(1)搭设下部钢筋支撑架的具体措施:在距梁底标高竖向高出1000mm处,每横向@3000mm处用横钢管支撑于排架上,做成下第一排钢筋的支撑架,并将下第一排钢筋按设计顺序放于支撑架上,依此类推,直至下三、下四,所有下部钢筋搭设完成。
(2)搭设上部钢筋支撑架的措施:首先搭设上部钢筋最下一排的支撑架,并设计要求放置好该排钢筋,依次类推,直至上部钢筋支撑架全部完成,但搭设好最上一排钢筋支架时,由于上一排钢筋弯钩长达几米,需经电渣压力焊才能完成,因此不能直接将上一排钢筋置于钢筋架上,须在距上一排钢筋支撑架高出2000mm处另搭设钢筋焊接用的支撑架,将上一排钢筋按设计顺序悬吊其上,进行电渣压力焊,弯钩焊接施工完毕,松开钢筋下落至上一排钢筋支撑架上,施工过程中,特别要注意上一排支撑架的标高,一定要保证上一排钢筋置于其上时,刚好是它们在梁面所处的位置。
(四)钢筋的安装与就位
钢筋安装顺序:搭钢管搁架—分层铺设下部纵筋—分层挂吊上部纵筋—套箍筋—放吊筋—拆搁架下横杆、下纵筋与箍筋绑扎固定—上纵筋与箍筋绑扎固定—梁底保护层—骨架就位—绑扎吊筋、柱节点箍筋—穿负筋、腰筋等。
(1)绑扎下部钢筋,按顺序抽走下一排筋支撑面,下落下一排钢筋至梁底部位,并绑扎。放置横向@1500mmΦ25分隔筋;抽走下二排支撑面,下落第二排钢筋至设计要求部位,并绑扎,依此类推,直至所有下部钢筋绑扎完毕。绑扎上部钢筋,首先绑扎上第一排钢筋,完工后,松开并抽走上第一排钢筋支撑面,然后从梁一端向另一端依次开上二排钢筋支撑点。一边松开,一边将钢筋上提至正确位置,同时插进隔筋,绑扎固定上二排筋,依此类推,直至上部钢筋绑扎完毕。
(2)梁上部的主筋接头要求设置在跨中1/3跨长内,下部主筋接头要求设在靠近支座1/3跨长内。由于梁内主筋多,主筋下料时,必须考虑并调整好每根钢筋的接头位置,以保证主筋的焊接接头相互错开并满足现行规范要求。
(3)在梁底模的两侧划线定出每排16根Φ32纵筋的分布位置,同时确定它们各自在柱节点的位置(位于哪两根柱主筋之间),主筋排列必须按次序对号入座。
(4)安装梁柱筋要注意梁与梁之间的协调,按先主梁后其余梁的顺序,纵筋依次交叉穿插,上下交替搁置,以保证主筋在梁内的设计位置。
(5)安装柱节点箍筋时,必须事先确定的位置和数量,在主筋铺设的同时将柱箍放置在各层主筋之间。待大梁钢筋骨架就位后,按由上至下的顺序将柱箍同柱主筋绑扎固定。柱节点箍筋不得少放、漏放。
(6)大梁上下几排钢筋在绑扎就位时要保证其上下对齐形成垂直的钢筋间隙,以便混凝土灌注和振捣。
(7)梁底保护层:鉴于梁钢筋骨架重,底筋高度不一,用细石混凝土和钢筋丝网片特制了两种厚度的高强度夹丝保护层垫块(以防压碎)。保护层垫块成排布置,统一垫在主筋下(排距1.5m),在梁骨架就位前放置好。
(8)梁钢筋安装绑扎时,必须在梁底模两端划定出每排中X32纵筋的分布位置,以确定各自在柱节点的位置,并且对号入座。由于转换梁内钢筋骨架重,为保证保护层厚度,用短钢筋头作垫块,保护层垫块成排布置,排距1.0m,统一垫在主筋下,在梁的骨架就位前放置好。转换梁底部钢筋绑扎的原则是次梁压主梁,板筋压梁筋。即先绑Y轴向主梁,再绑璐由向主梁及板筋,然后绑y方向次梁及板筋。暗梁及板底部钢筋绑扎完后,开始放置马凳,马凳纵横间距约0.7m。马凳用Φ25钢筋制作。
(9)转换层梁柱点处,钢筋分布较为密集,应先穿高梁钢筋(高梁钢筋底筋有弯折),然后再穿低梁钢筋(低梁钢筋锚入高梁中)。
(10)一般转换梁底筋及其密集,可与设计院、监理、甲方协商,在转换梁中底筋下排X32钢筋中各抽取一至两根放到最上排。这样钢筋间距拉大,有利于混凝土浇筑。
(11)由于钢筋复杂,浇筑硅时派专人检查及保护钢筋,避免钢筋变形移位。
结语:
由此可见,梁式转换层钢筋连接是保证保障转换层技术质量的重要环节。必须重视梁式转换层钢筋连接的下料与翻样,在施工安装过程中保障受力钢筋的准确就位。本文结合转换层的受力性能,对钢筋混凝土梁式转换层的钢筋的连接和绑扎技术进行了系统的研究,提出转换层的跨度和承受的荷载都很大,其配筋较多,而且钢筋骨架的高度较高,施工时应采取措施保证钢筋骨架的稳定和便于钢筋的布置。
参考文献:
[1] 王永德;;高层建筑结构转换层施工技术的应用[J];山西建筑;2010年02期
[2] 李永贵,王非平. 南宁市新华书店图书大厦转换梁裂缝控制措施[J]建筑技术 , 2006,(04) .
[3] 李鹏;张玉红;;高层建筑转换层施工质量控制[J];中国新技术新产品;2010年01期
[4] 周先祥. 某砖混结构住宅楼现浇板裂缝原因分析及加固处理[J]安徽建筑 , 2005,(03) .
关键词:高层建筑 钢筋混凝土 梁式转换层 钢筋连接
Abstract: with the development of society, the progress of science and technology, diversification of city construction. Many high-rise buildings to the development of multi-function, multi-purpose direction, in the design and construction practice, girder transfer floor has been widely used and recognized at home and abroad; some have been built with the conversion layer of high-rise building conversion layer, reinforced concrete beam accounted for more than 70%, it realizes the change of architectural space upper and lower structure.
Key words: high-rise buildings of reinforced concrete girder transfer floor reinforcement connection
中图分类号: [TU208.3] 文献标识码:A 文章编号:2095-2104(2013)
一、钢筋安装顺序
高层建筑梁式转换层钢筋用量大、型号多;转换梁截面大,梁上下钢筋布置错综复杂。准确放样与下料、合理安排好钢筋就位次序尤为重要。放样时考虑好钢筋之间的穿插避让关系,确定制作尺寸和绑扎顺序,钢筋工程安装顺序如下.
搭钢管支架—分层排布主梁上部纵筋、套箍筋—梁上部主筋与箍筋绑扎牢固—拆支架横杆—洞口加固筋就位—穿梁下部主筋和腰筋、垫好梁下保护层短筋—下部主筋与箍筋绑扎牢固—铺放板底双向双层钢筋—逐层向上铺设暗梁处的中间部位腰筋—上下水电气管线敷设、钢筋马凳的焊接固定—铺放及绑扎板上部钢筋及表面加强筋。
二、转换层钢筋的连接与安装
(一)鋼筋翻样与下料
转换大梁的含钢量大,主筋长,布置密,在两梁相交的柱节点区上下共有几十层上百根主筋在此“相聚”,加上腰筋、柱筋等,主筋还须弯起锚固,众筋“抢位”现象十分突出。任何一根主筋的就位错误,均会造成大量的返工。因此,准确地翻样和下料是钢筋顺利施工的前提。
(1)钢筋翻样前必须弄清设计意图;审核、熟悉设计文件及有关说明;掌握
现行规范的有关规定。翻样时要结合实际并考虑方便施工。
(2)一般设计设计转换大梁的主筋在柱节点区均弯起锚固,施工难度大。可与设计单位协商解决,如:大梁的最上一排面筋向下弯并锚固至底筋以上;底筋的最下一排主筋尽量靠柱边上弯25d,其余主筋全部取销弯锚,负筋亦不起弯,均伸至弯起筋即可(柱截面大,锚固长度满足要求)。这样一来,增大了节点空间,为混凝土的灌注和振捣提供了条件。
(3)梁上部的主筋接头要求设置在跨中1/3跨长内,下部主筋接头要求设在靠近支座1/3跨长内。由于梁内主筋多,主筋下料时,必须考虑并调整好每根钢筋的接头位置,以保证主筋的焊接接头相互错开并满足现行规范要求。
(4)为方便钢筋的安装就位,满足上述规范要求,必须对所有梁主筋按就位顺序进行编号。
(5)梁箍筋大,下料时要注意对焊接头位置,避免接头出现在箍筋的弯折处。
(二)各部位钢筋连接方式
转换层中钢筋的种类繁多,不同位置钢筋受力情况也不尽相同,因此,各部位应综合受力情况、施工难度、经济效益等采用不同的连接方式。
(1)转换层大梁的主筋是转换层中最重要的受力单元,应采用最可靠且对钢 筋无损害的连接方式,通常采用冷挤压连接法。
(2)转换层柱钢筋、剪力墙竖向分布筋宜采用电渣压力焊。
(3)转换层主梁腰筋及箍筋、联系梁主筋、板钢筋一般采用闪光焊接。
(4)其他受力较次要部位,如联系梁架力筋及箍筋可采用绑扎连接。
(三)钢筋支撑架的搭设
在钢筋成型及绑扎施工过程中,由于钢筋特长,只能在施工现场进行连接,在连接时,必须搭设钢筋支撑架,支撑架的搭设是便于钢筋绑扎的关键。
(1)搭设下部钢筋支撑架的具体措施:在距梁底标高竖向高出1000mm处,每横向@3000mm处用横钢管支撑于排架上,做成下第一排钢筋的支撑架,并将下第一排钢筋按设计顺序放于支撑架上,依此类推,直至下三、下四,所有下部钢筋搭设完成。
(2)搭设上部钢筋支撑架的措施:首先搭设上部钢筋最下一排的支撑架,并设计要求放置好该排钢筋,依次类推,直至上部钢筋支撑架全部完成,但搭设好最上一排钢筋支架时,由于上一排钢筋弯钩长达几米,需经电渣压力焊才能完成,因此不能直接将上一排钢筋置于钢筋架上,须在距上一排钢筋支撑架高出2000mm处另搭设钢筋焊接用的支撑架,将上一排钢筋按设计顺序悬吊其上,进行电渣压力焊,弯钩焊接施工完毕,松开钢筋下落至上一排钢筋支撑架上,施工过程中,特别要注意上一排支撑架的标高,一定要保证上一排钢筋置于其上时,刚好是它们在梁面所处的位置。
(四)钢筋的安装与就位
钢筋安装顺序:搭钢管搁架—分层铺设下部纵筋—分层挂吊上部纵筋—套箍筋—放吊筋—拆搁架下横杆、下纵筋与箍筋绑扎固定—上纵筋与箍筋绑扎固定—梁底保护层—骨架就位—绑扎吊筋、柱节点箍筋—穿负筋、腰筋等。
(1)绑扎下部钢筋,按顺序抽走下一排筋支撑面,下落下一排钢筋至梁底部位,并绑扎。放置横向@1500mmΦ25分隔筋;抽走下二排支撑面,下落第二排钢筋至设计要求部位,并绑扎,依此类推,直至所有下部钢筋绑扎完毕。绑扎上部钢筋,首先绑扎上第一排钢筋,完工后,松开并抽走上第一排钢筋支撑面,然后从梁一端向另一端依次开上二排钢筋支撑点。一边松开,一边将钢筋上提至正确位置,同时插进隔筋,绑扎固定上二排筋,依此类推,直至上部钢筋绑扎完毕。
(2)梁上部的主筋接头要求设置在跨中1/3跨长内,下部主筋接头要求设在靠近支座1/3跨长内。由于梁内主筋多,主筋下料时,必须考虑并调整好每根钢筋的接头位置,以保证主筋的焊接接头相互错开并满足现行规范要求。
(3)在梁底模的两侧划线定出每排16根Φ32纵筋的分布位置,同时确定它们各自在柱节点的位置(位于哪两根柱主筋之间),主筋排列必须按次序对号入座。
(4)安装梁柱筋要注意梁与梁之间的协调,按先主梁后其余梁的顺序,纵筋依次交叉穿插,上下交替搁置,以保证主筋在梁内的设计位置。
(5)安装柱节点箍筋时,必须事先确定的位置和数量,在主筋铺设的同时将柱箍放置在各层主筋之间。待大梁钢筋骨架就位后,按由上至下的顺序将柱箍同柱主筋绑扎固定。柱节点箍筋不得少放、漏放。
(6)大梁上下几排钢筋在绑扎就位时要保证其上下对齐形成垂直的钢筋间隙,以便混凝土灌注和振捣。
(7)梁底保护层:鉴于梁钢筋骨架重,底筋高度不一,用细石混凝土和钢筋丝网片特制了两种厚度的高强度夹丝保护层垫块(以防压碎)。保护层垫块成排布置,统一垫在主筋下(排距1.5m),在梁骨架就位前放置好。
(8)梁钢筋安装绑扎时,必须在梁底模两端划定出每排中X32纵筋的分布位置,以确定各自在柱节点的位置,并且对号入座。由于转换梁内钢筋骨架重,为保证保护层厚度,用短钢筋头作垫块,保护层垫块成排布置,排距1.0m,统一垫在主筋下,在梁的骨架就位前放置好。转换梁底部钢筋绑扎的原则是次梁压主梁,板筋压梁筋。即先绑Y轴向主梁,再绑璐由向主梁及板筋,然后绑y方向次梁及板筋。暗梁及板底部钢筋绑扎完后,开始放置马凳,马凳纵横间距约0.7m。马凳用Φ25钢筋制作。
(9)转换层梁柱点处,钢筋分布较为密集,应先穿高梁钢筋(高梁钢筋底筋有弯折),然后再穿低梁钢筋(低梁钢筋锚入高梁中)。
(10)一般转换梁底筋及其密集,可与设计院、监理、甲方协商,在转换梁中底筋下排X32钢筋中各抽取一至两根放到最上排。这样钢筋间距拉大,有利于混凝土浇筑。
(11)由于钢筋复杂,浇筑硅时派专人检查及保护钢筋,避免钢筋变形移位。
结语:
由此可见,梁式转换层钢筋连接是保证保障转换层技术质量的重要环节。必须重视梁式转换层钢筋连接的下料与翻样,在施工安装过程中保障受力钢筋的准确就位。本文结合转换层的受力性能,对钢筋混凝土梁式转换层的钢筋的连接和绑扎技术进行了系统的研究,提出转换层的跨度和承受的荷载都很大,其配筋较多,而且钢筋骨架的高度较高,施工时应采取措施保证钢筋骨架的稳定和便于钢筋的布置。
参考文献:
[1] 王永德;;高层建筑结构转换层施工技术的应用[J];山西建筑;2010年02期
[2] 李永贵,王非平. 南宁市新华书店图书大厦转换梁裂缝控制措施[J]建筑技术 , 2006,(04) .
[3] 李鹏;张玉红;;高层建筑转换层施工质量控制[J];中国新技术新产品;2010年01期
[4] 周先祥. 某砖混结构住宅楼现浇板裂缝原因分析及加固处理[J]安徽建筑 , 2005,(03) .