首钢第一烧结厂原有的五台62.5米~2烧结机于1959年建成。采用苏联四十年代的陈旧工艺,这种旧的工艺设备造型不合理,操作条件差,粉尘污染十分严重,每天外排的粉尘量约40吨左右。为了提高烧结机的自动化水平,消除对周围环境的污染,首钢公司决定对第一烧结厂进行大修改造。这项工程在不停产的条件下,从1981年6月开始施工。工程特点是工程量大(仅钢结构安装量就有一万吨),而且边生产边施工(施工现场温度高、灰尘弥漫),突出的矛盾是场地窄小,这些是制定施工方案时必须考虑的。
The original five 62.5m~2 sintering machines at Shougang No. 1 Sintering Plant were built in 1959. Using the old craftsmanship of the Soviet Union in the 1940s, this old process equipment was unreasonable, operating conditions were poor, and dust pollution was very serious. The amount of dust discharged every day was about 40 tons. In order to improve the automation level of the sintering machine and eliminate the pollution to the surrounding environment, Shougang Company decided to renovate the first sintering plant. The project began construction in June 1981 under conditions of non-stop production. The engineering feature is the large amount of work (only 10,000 tons of steel structure installed), and the construction of the production side (high temperature on the construction site, dust filled), the prominent contradiction is the narrow site, these are the considerations when formulating the construction plan of.