论文部分内容阅读
公司无电区建设总体情况“十一五”和“十二五”2006~2015年,公司系统累计完成无电地区电力建设投资381亿元,为191.7万户749.5万无电人口解决了通电问题,实现了公司经营区大电网延伸覆盖下的“户户通电”。需要通电的乡村主要分布西藏,新疆阿勒泰、和田、库尔勒,四川的甘孜阿坝及凉山州,青海海南、海西和果洛州,甘肃的张掖、甘南等地区。
The Company has no electricity area construction overall situation “Eleventh Five-Year ” and “Twelve-Five ” From 2006 to 2015, the company system completed a total investment of 38.1 billion yuan electric power construction in areas without electricity, to 1.177 million 749.5 million people without electricity Solve the power problem, to achieve the company’s operating area under the coverage of large power grid “household power ”. The villages that need electricity are mainly distributed in Tibet, Xinjiang Altay, Wada, Korla, Ganzi Aba and Liangshan Prefecture in Sichuan, Hainan, Haixi and Guoluo in Gansu, Zhangye and Gannan in Gansu and other areas.