论文部分内容阅读
一、前言由于原电解厂房十分陈旧,又是小耳阳极电解,因此,决定在原车间附近建设一个采用大型阳极并有最新技术水平的电解车间。新车间于1978年6月建成,并立即投入了试生产,9月份旧车间全面停产,10月份新车间就达到了月产4000吨的设计产量,从1979年4月起,每月增产约600吨,至今操作都很顺利,各项作业指标均达到了设计能力。
I. Preface As the original electrolytic plant is very old, but also a small ear electrolysis, therefore, decided to build a near the original workshop using a large anode and the latest technology level electrolysis plant. The new workshop was completed in June 1978 and immediately put into trial production. In September, the old workshop was completely discontinued. In October, the new workshop reached a designed output of 4,000 tons per month. From April 1979, the monthly production increase was about 600 Ton, so far the operation is very smooth, the operating indicators have reached the design capacity.