六连体等截面筒仓施工中 ,采用模板、挂架相互提升施工方案 ,只需投入少量的钢管、槽钢、模板等 ,组装方便 ,时间短 ,提升速度虽慢于滑模 ,但对于30多米高的筒仓而言 ,总工期并不比滑模施工长 ,且易于控制质量 ,成本低。
In the construction of six-section cross-section silos, the use of templates and pylon to enhance the construction plan of each other requires only a small amount of steel pipes, channel steels, and stencils. The assembly is convenient, the time is short, and the lifting speed is slower than the sliding mode, but for 30 In the case of Domi Heights silo, the total construction period is not longer than the construction of sliding mode, and the quality is easy to control and the cost is low.