论文部分内容阅读
第十二条新建500千伏及以上架空电力线路,其边线垂直投影外侧五米内所跨越的住宅建筑物,电力建设单位应当依法实施拆迁并给予补偿。新建220千伏及以下架空电力线路一般不得跨越房屋,特殊情况需要跨越房屋时,电力建设单位应当采取增加杆塔高度等措施,保证被跨越房屋的安全。达到国家规定安全距离的,不实施拆迁和补偿;无法达到国家规定安全距离的,由电力建设单位依法实施拆迁并给予补偿。【释义】本条是关于新建线路跨越房屋及拆除补偿的规定。
Article 12 New 500 kV and above overhead power lines shall be newly built. The sidelines of the residential buildings and buildings within the distance of 5 meters outside the vertical projection shall be demolished and compensated according to law. New 220 kV and below overhead power lines generally can not cross the house, special circumstances need to cross the house, the power construction unit should take measures to increase the height of the tower to ensure that the safety of being across the house. When reaching the safety distance stipulated by the state, the demolition and compensation will not be implemented; if the safety distance can not be achieved as prescribed by the state, the power construction unit shall implement the demolition and compensation according to law. 【Explanation】 This section is about the new line across the house and demolition compensation provisions.