河南河务局1999年汛后防洪主体工程大部分已经开工,截至11月12日,共计完成土方87.77万m~3,投资1637万元。今年汛后,黄委安排河南黄河大堤加高、加培、河道整治、险点处理、堤顶硬化及沁河治理等六大类91项防洪工程建设任务,土方3916万m~3,石方26万m~3,投资8亿元。为建立健康有序的黄河防洪工程建设市场,河南河务局严格按照水利部《堤防工程建设管理暂行办法》和《水利工程建设项目施工招标投标管理规定》,本着公开、公平、公正的原则,对1999
Most of the flood control main works of Henan Bureau of Heilongjiang River after flood control in 1999 have been started. As of November 12, a total of 877,700 m 3 of earthwork has been completed with an investment of 16.37 million yuan. After the flood season this year, the Yellow River Conservancy arranged for the construction of 91 flood control projects in six major categories, including the Yellow River embankment in Henan Province, the increase of peasants, river courses, the treatment of dangerous points, the hardening of embankments and the treatment of Qinhe River. The earthwork of 39.16 million m 3, 260,000 m ~ 3, invest 800 million yuan. In order to establish a healthy and orderly market for the flood control construction of the Yellow River, the Henan River Bureau strictly follows the Interim Measures for the Administration of Dike Construction and Management of Water Conservancy and the Provisions on Tendering and Bidding for Construction of Water Conservancy Projects. Based on the principle of openness, fairness and impartiality , To 1999