论文部分内容阅读
为争取乌江一号机提前发电,抢工期,根据土建进度和工期安排,一号发电机定子在机坑外组合下线,整体吊入机坑就位安装。本定子分四瓣组合,定子铁心外径11035mm,内径9480mm,铁心长度2400mm,机座外径11850mm,机座高4050mm,组合后定子总重300T,厂内有一台300T×2桥机,双钩,每钩载荷300T,吊钩起吊高度离安装间地面9.7米,定子结
In order to fight ahead of Wujiang Unit 1 power generation and grab the construction period, according to the progress of construction and construction schedule, the generator stator in the pit outside the combination of assembly line, the whole hanging into the pit installation. The stator is divided into four combinations. The outer diameter of the stator core is 11035mm, the inner diameter is 9480mm, the length of the core is 2400mm, the outer diameter of the base is 11850mm and the base is 4050mm high. The combined total weight of the stator is 300T. There is a 300Tx2 bridge machine in the factory, Hook load 300T, lifting hook lifting height of 9.7 meters from the ground between the installation, the stator knot