在单台盾构掘进的隧道中,盾构通常是在掘进完成后在洞外进行拆卸。在工期要求紧的长大隧道中,在同一隧道中的两台盾构相向掘进施工,需要在隧道会合点处对两台盾构进行对接拆卸。对接拆卸要求安全可靠,在盾构的结构设计、工艺制定时就应充分考虑。以广深港客运专线狮子洋隧道工程为例,叙述了对接拆卸的盾构采用双层独立盾壳、主要部件分块构造、限制单件重量、预留超前钻导孔及轨道式后配套拖车等结构设计应采用的技术措施,对拆卸前的准备工作和拆卸处进行多层注浆加固的方法进行了介绍。重点介绍盾构对接拆卸步骤,分别叙述后配套拖车的拆卸、主机部件的拆卸、主驱动组件的拆卸和刀盘拆卸的步骤。
In a single TBM tunnel, the shield is usually disassembled outside the tunnel after the excavation is complete. In tunnels with tight deadlines, two shield tunneling machines in the same tunnel need to be disassembled at the junction of the tunnels. Docking demolition requires safe and reliable, in the shield structure design, process development should be fully considered. Taking the Shiziyang tunnel project of Guangzhou-Shenzhen-Hong Kong Passenger Dedicated Line as an example, the shield of the docking demolition is described with a double-layer independent shield shell. The main components are divided into blocks, limiting the weight of a single piece, reserving the leading drilled holes and the track- Such as structural design and other technical measures should be used to prepare the demolition of the demolition work and multi-layer grouting reinforcement method is described. It focuses on the steps of docking and dismantling the shield, detailing the disassembly of the auxiliary trailer, the disassembly of the mainframe components, the disassembly of the main drive assembly and the removal of the cutterhead.