论文部分内容阅读
1985年全国生产连铸坯501.6万吨,完成了国家计划生产连铸坯500万吨的任务。全年新建投产7台连铸机(合肥、韶关、通化、南京钢铁厂、马钢二炼钢、太钢三炼钢、上钢一厂二转炉车间等各一台),新增设计能力合计73万吨。武钢二炼钢厂实现了全连铸和三明钢铁厂小方坯连铸机达到设计水平受到部的嘉奖。太钢三炼钢厂立式板坯连铸机的建成投产结束了我国合金钢电炉钢厂没有连铸的历史。1985年全国连铸生产技术经济指标见表1~2。
In 1985, the country produced 5.016 million tons of continuous casting slabs, completing the task of producing 5 million tons of continuous casting slabs by the state. Newly put into operation 7 sets of continuous casting machines (one each from Hefei, Shaoguan, Tonghua, Nanjing Steel Plant, Maansteel II, Taigang No.3 steelmaking plant and Shanghai Steel First Plant II converter workshop) 730,000 tons. WISCO completed the second steelmaking plant and Sanming Steel Plant billet caster to achieve the design level by the Ministry of awards. TISCO third steel vertical slab caster completion put into operation the end of the history of China’s steel electric steel mill without continuous casting. In 1985 the country’s continuous casting production technology and economic indicators in Table 1 ~ 2.