日钢第二炼钢厂4座120吨转炉相继投产后,炉体中压水水冷配管系统因漏水导致非计划停炉频繁,严重影响了转炉正常的生产节奏。针对此现状二炼钢厂通过去除原转炉本体风冷系统,利用耳轴、托圈内原风冷通道为进、回水冷却通道,炉体总进、回冷却水管布置在近炉底侧托圈下部的方法,杜绝了此类事故发生。取消炉腹空冷后,转炉本体外壳与托圈内圈的间距未发生明显变化,改进比较成功。
After Nippon Steel’s No. 2 Steel Works, four 120-ton converters were put into operation one after another, the unplanned shut-down of the pressure water-cooled piping system in the furnace resulted in frequent unplanned shutdowns, seriously affecting the normal production pace of the converter. For the status quo of the second steel mill by removing the original converter body air-cooled system, the use of the trunnion, the ring of the original air-cooled channel into the backwater cooling channel, the total furnace inlet and return cooling pipes arranged near the underside of the furnace near the ring The lower part of the way to eliminate such accidents. After the abolition of the air-blast stove, the converter body shell and the inner ring of the carrier ring did not change significantly to improve the more successful.