摘 要:长输管道施工中,山区陡坡地段一直是油气管道施工的难点。而陡坡溜管施工作为一种陡坡施工的方法其施工工艺已逐步成熟,其主要包括降坡开挖、主管道预制与管端处理、防腐层保护、溜管施工、坡顶连头,本文阐述了各工艺的施工技术要求,分析总结该技术在中缅天然气管道工程中的应用,通过制定和实施一系列措施保证管道陡坡段溜管施工的顺利进行。
关键词: 陡坡 溜管 施工工艺
Abstract : Pipeline construction of a long distance, mountain steep slope area is always a difficult problem in oil and gas pipeline construction. And thesteep pipe construction as a method of steep slope construction the construction technology has gradually matured, which mainly includesslope excavation, prefabrication and pipe main pipe end treatment,anti-corrosion layer of protection, construction, the top head chute.This paper expounds the construction technology requirements of theprocess, analysis and application of this technology are summarized in the China Myanmar gas pipeline project, through the development and implementation of a series of measures to ensure the steep section of the pipeline pipe construction.
THE Keywords:steepchuteconstruction technology
中图分类号:TE89 文献标识码:A
1、工程概况
长输管道穿越山区陡坡地段由于纵横坡度大、易受滑坡、塌方、泥石流等地质灾害的威胁, 因而成为施工过程中的关键控制点。而陡坡溜管施工作为一种陡坡施工的方法其施工工艺已逐步成熟,其主要包括降坡开挖、主管道预制与管端处理、防腐层保护、溜管施工、坡顶坡底连頭。中缅天然气管道(国内段)线路途经都匀市凯口镇朵罗村,整个管线所经地区为突出状,坡陡且险,地面岩层基岩突露,主要为灰岩,该段陡坡总长度为140m,高差为110m。经现场实测,该段陡坡坡顶为4m土路一条,为村庄唯一的主通道,陡坡坡度现场测量为60°,总体来说施工难度较大。因此在分析了多种方法后,排除了传统的自下至上卷扬机牵引施工法,由于现场坡度过大,在管沟降坡以及开挖过程中出现了多个纵向变坡点,且高点处施工平台难以搭设,都给该方法造成了不少困难,因此,最终机组决定采用陡坡溜管施工工艺进行施工。
2、陡坡溜管施工工艺
陡坡施工采用溜管的方进行式施工,经对比分析后,决定选用机械开挖方式对陡崖下半段进行机械开挖,利用挖出的管沟土垫作业带,上半段范围内采用人工开凿钻孔爆破的方式。管道在陡坡上方进行整体预制后 “溜管”。主要施工工艺流程:降坡开挖、主管道预制与管端处理、防腐层保护、溜管施工、坡顶连头。
2.1 降坡开挖
由于该段陡坡坡度较大,若按设备行走坡度进行降坡, 土方量将非常大。因此,确定对陡坡下部70m范围内(26°区段)进行降坡处理,降坡后直接进行管沟开挖管道完成管沟开挖后,对其进行溜管法施工。陡坡上方60m段(60°角度)采用人工凿岩钻孔爆破的方式进行施工。
2.2 主管道预制及管端处理
管沟开挖完成后,应首先在坡顶预制主管道,由于陡坡斜面存在转角,预制的管道还包含弯头和弯管,增加溜管的难度。根据现场情况,预制为6接1的管段,并采用电动单筒160KN卷扬机配合2台挖掘机进行牵引,安全系数符合施工要求;靠近上方管段焊接一已开孔(3处)的短接,中央0点为使用陡坡上方的卷扬机进行牵引,控制管道溜管过程中管道下滑的速度,两侧3点9点位使用挖掘机辅助牵引,控制管道下滑的方向,防止管道溜管过程中向两侧倾倒。
2.3 防腐层保护
陡坡沟底段部分为石方,由于坡度较大,沟底铺设细土袋子的方法难以保证管道防腐层不受损伤,同时为防止管道在下滑过程中因温度过高而损伤防腐层,结合以往工程施工经验,溜管前在管道外层包覆一层厚4 mm 的钢板,每组钢板1.5m宽,经过加工弯曲,直接包裹在管子外围,每组钢板搭接不少于200mm,包裹方向为自上至下,特别注意其搭接方向,每道搭接面上均为顺气流下方的钢板在上进行搭接,防止管道溜管过程中钢板的搭接焊道出现进行大范围摩擦。钢板的使用有效保证了管道防腐层的安全,保证了管道防腐层的质量
2.4 溜管施工
将预制的主管道整体包裹后,连接好管端的钢丝绳,利用2 台吊管机将管道整体吊起,缓慢移向坡边, 到达斜坡位置后,将最后1 台吊管机撤掉并挂上牵引钢丝,另1台吊管机将管道缓慢放至预先开好的引沟内,再向坡下运送。管道坡顶方向使用卷扬机进行牵引,并缓慢放绳,两侧挖掘机配合调整方向。溜管时应注意提前标注出预制管道的重心位置,当管道溜管超过重心点后,撤去吊管机,由卷扬机缓慢放绳,管子缓慢下滑,直至溜管到位。
2.5 坡顶连头
溜管段管道安装就位后,应首先抓紧进行坡顶管段与主线路的连头,形成管道的牵引点并完成回填后再返至坡底部分进行连头施工。坡底段施工沿顺气流方向焊接,直至焊接至坡底与坡底已焊接管道连头组对。
3、结束语
通过使用改良后的陡坡溜管施工方法,中缅管道顺利的完成了陡坡溜管,解决了管道施工上的又一个难题。该技术的使用不但缩短了施工工期,降低了施工成本,还取得了良好的经济效益和社会效益,为以后今后类似的难点施工提供了借鉴和参考。
参 考 文 献
1朱建孙立浩 《长输油气管道山区陡坡地段施工技术》 管道技术与设备2003年
2 高志川 刁风东 霸磊 杨明 《陡坡溜管施工在西二线管道工程中的应用》油气储运2012年12月第31卷第12期
关键词: 陡坡 溜管 施工工艺
Abstract : Pipeline construction of a long distance, mountain steep slope area is always a difficult problem in oil and gas pipeline construction. And thesteep pipe construction as a method of steep slope construction the construction technology has gradually matured, which mainly includesslope excavation, prefabrication and pipe main pipe end treatment,anti-corrosion layer of protection, construction, the top head chute.This paper expounds the construction technology requirements of theprocess, analysis and application of this technology are summarized in the China Myanmar gas pipeline project, through the development and implementation of a series of measures to ensure the steep section of the pipeline pipe construction.
THE Keywords:steepchuteconstruction technology
中图分类号:TE89 文献标识码:A
1、工程概况
长输管道穿越山区陡坡地段由于纵横坡度大、易受滑坡、塌方、泥石流等地质灾害的威胁, 因而成为施工过程中的关键控制点。而陡坡溜管施工作为一种陡坡施工的方法其施工工艺已逐步成熟,其主要包括降坡开挖、主管道预制与管端处理、防腐层保护、溜管施工、坡顶坡底连頭。中缅天然气管道(国内段)线路途经都匀市凯口镇朵罗村,整个管线所经地区为突出状,坡陡且险,地面岩层基岩突露,主要为灰岩,该段陡坡总长度为140m,高差为110m。经现场实测,该段陡坡坡顶为4m土路一条,为村庄唯一的主通道,陡坡坡度现场测量为60°,总体来说施工难度较大。因此在分析了多种方法后,排除了传统的自下至上卷扬机牵引施工法,由于现场坡度过大,在管沟降坡以及开挖过程中出现了多个纵向变坡点,且高点处施工平台难以搭设,都给该方法造成了不少困难,因此,最终机组决定采用陡坡溜管施工工艺进行施工。
2、陡坡溜管施工工艺
陡坡施工采用溜管的方进行式施工,经对比分析后,决定选用机械开挖方式对陡崖下半段进行机械开挖,利用挖出的管沟土垫作业带,上半段范围内采用人工开凿钻孔爆破的方式。管道在陡坡上方进行整体预制后 “溜管”。主要施工工艺流程:降坡开挖、主管道预制与管端处理、防腐层保护、溜管施工、坡顶连头。
2.1 降坡开挖
由于该段陡坡坡度较大,若按设备行走坡度进行降坡, 土方量将非常大。因此,确定对陡坡下部70m范围内(26°区段)进行降坡处理,降坡后直接进行管沟开挖管道完成管沟开挖后,对其进行溜管法施工。陡坡上方60m段(60°角度)采用人工凿岩钻孔爆破的方式进行施工。
2.2 主管道预制及管端处理
管沟开挖完成后,应首先在坡顶预制主管道,由于陡坡斜面存在转角,预制的管道还包含弯头和弯管,增加溜管的难度。根据现场情况,预制为6接1的管段,并采用电动单筒160KN卷扬机配合2台挖掘机进行牵引,安全系数符合施工要求;靠近上方管段焊接一已开孔(3处)的短接,中央0点为使用陡坡上方的卷扬机进行牵引,控制管道溜管过程中管道下滑的速度,两侧3点9点位使用挖掘机辅助牵引,控制管道下滑的方向,防止管道溜管过程中向两侧倾倒。
2.3 防腐层保护
陡坡沟底段部分为石方,由于坡度较大,沟底铺设细土袋子的方法难以保证管道防腐层不受损伤,同时为防止管道在下滑过程中因温度过高而损伤防腐层,结合以往工程施工经验,溜管前在管道外层包覆一层厚4 mm 的钢板,每组钢板1.5m宽,经过加工弯曲,直接包裹在管子外围,每组钢板搭接不少于200mm,包裹方向为自上至下,特别注意其搭接方向,每道搭接面上均为顺气流下方的钢板在上进行搭接,防止管道溜管过程中钢板的搭接焊道出现进行大范围摩擦。钢板的使用有效保证了管道防腐层的安全,保证了管道防腐层的质量
2.4 溜管施工
将预制的主管道整体包裹后,连接好管端的钢丝绳,利用2 台吊管机将管道整体吊起,缓慢移向坡边, 到达斜坡位置后,将最后1 台吊管机撤掉并挂上牵引钢丝,另1台吊管机将管道缓慢放至预先开好的引沟内,再向坡下运送。管道坡顶方向使用卷扬机进行牵引,并缓慢放绳,两侧挖掘机配合调整方向。溜管时应注意提前标注出预制管道的重心位置,当管道溜管超过重心点后,撤去吊管机,由卷扬机缓慢放绳,管子缓慢下滑,直至溜管到位。
2.5 坡顶连头
溜管段管道安装就位后,应首先抓紧进行坡顶管段与主线路的连头,形成管道的牵引点并完成回填后再返至坡底部分进行连头施工。坡底段施工沿顺气流方向焊接,直至焊接至坡底与坡底已焊接管道连头组对。
3、结束语
通过使用改良后的陡坡溜管施工方法,中缅管道顺利的完成了陡坡溜管,解决了管道施工上的又一个难题。该技术的使用不但缩短了施工工期,降低了施工成本,还取得了良好的经济效益和社会效益,为以后今后类似的难点施工提供了借鉴和参考。