对宁波-舟山港梅山保税港区1#-5#集装箱码头项目3#-5#泊位水工桩基设计、施工等进行了合理优化;主要对试桩方案、引桥钻孔桩外套筒长度及码头大管桩长度等进行优化,累计共节约投资6867849.52元。
The design and construction of hydraulic foundations for 3 # -5 # berths in No. 1 # -5 container terminal of Meishan Bonded Port Area in Ningbo-Zhoushan Port are optimized. And the length of the large pipe pile terminal optimization, total investment of 6867849.52 yuan.