论文部分内容阅读
【摘 要】产芝灌区灌溉面积2.33万hm2,属大型灌区,是青岛市最大的农业灌区,也是莱西市最重要的农业生产基地。该灌区兴建于六十年代,自建成以来,发挥了很大的灌溉效益,为莱西市的农业和农村经济发展做出了巨大贡献。但由于年久失修,工程严重老化、退化,农业灌溉效益受到很大影响。实施产芝灌区续建配套与节水改造工程,可以对产芝灌区水资源进行优化调配,大幅度提高灌溉水的利用率,扩大和改善灌区灌溉面积充分发挥灌区效益。
【关键词】渠道防渗;节水灌溉
【Abstract】Irrigation production area of 23,300 Chicago hm2, is a large-scale irrigation, is the largest agricultural irrigation district of Qingdao City, is the most important city of Lacey agricultural production base. The irrigation construction in the 1960s, has since built and played a lot of irrigation efficiency, the Lacey City of agricultural and rural economic development has made great contributions. However, due to disrepair, engineering is aging and degradation, agricultural irrigation efficiency has been greatly affected. Implementation of the Chicago production and water-saving irrigation area renovation project, you can optimize production Chi irrigation water allocation, greatly improve the utilization of irrigation water, Irrigation expansion and improvement of irrigation efficiency into full play area.
【Key words】Channel seepage;Water-saving irrigation
1.工程概况
产芝水库总库容4.02亿m3,兴利库容1.76亿m3,灌区灌溉面积2.33万hm2,是青岛市最大的农业灌区,也是莱西市最重要的农业生产基地。产芝灌区兴建于60年代,自建成开灌以来,发挥了很大的灌溉效益,为莱西市的农业及农村经济发展做出了巨大贡献。但由于年久失修,工程严重老化,效益逐渐减退,严重制约了农业和农村经济的发展,总干渠又是产芝灌区最重要的输水干渠,因渠系年久老化失修,毁损严重,致使输水能力大大降低,灌溉周期延长,原设计过水能力16.1m3/s,由于渠道属土渠或风化岩,渗漏严重,现状实际过水能力仅为7.6m3/s。灌区灌溉周期设计为15d,现状实际需要30d,干渠水有效利用系数设计为0.78,1979年、1991年、1995年逐年锐减为0.65、0.59、0.45;原综合毛灌溉定额每亩为437m3,工程实施后毛灌溉定额每亩降低为287 m3;设计灌溉面积中现状仅能保灌1万hm2。灌区已经到了“有水放不下去,有水不能浇地”的状况,1998年经水利部立项批准,至2010年底,已实施完成了产芝灌区续建配套与节水改造1~10期工程。
2. 渠道防渗技术措施
按照工程规划,实施完成的产芝灌区配套三期(总干渠)工程,在工程多种防渗型式中,最具有代表性,主要内容为总干渠渠道防渗7Km,配套渠系建筑物48座,总干渠设计流量16.1 m3/s,加大流量19.3m3/s,比降为1/4000,当取不同断面时,设计水深如表1。
从表2可以看出,土工复合膜作防渗层,表面采用砼块作保护层是最佳方案。
根据渠道现在形状,总干渠采取了以下几种防渗措施:
2.1 0+000-0+150、3+350-1+150为梯形断面是大挖方段,且多为石方,水深2.0m,底宽9m,坡比为1:1-1:1.5。2+450-3+800为梯形断面,水深2.0m,底宽8m,且为筑方段,坡比为1:1,土质为砾石土,渗漏严重。采用乱石填腹、M15水泥砂浆砌预制C20砼板镶面,现浇砼护底的护砌形式。砌厚0.25m的M7.5块石填腹,外镶0.06m的C20砼板,现浇0.15×0.40的C20砼压顶,并现浇厚0.12m的C20砼护底。
2.2 0+150-0+350、1+150-2+450、6+510-6+900为矩形断面,底宽9-12米,边墙高2.5-3.0m已浆砌,采取对原渠道砌石脱落危险段局部拆除维修,并对原墙体进行勾缝处理,现浇0.15×0.40m的C20砼压顶,现浇厚0.10m的C20砼护底。
2.3 3+800-6+530为梯形断面,水深2.0m,底宽8m,土质较好,为半挖半填和挖方段。采用土工复合膜衬砌、砼工字块护坡、砼护底护砌型式。渠道整平夯实后坡比达到1:1.0,再铺土工复合膜,土工膜上衬砌厚0.08m的C25砼预制工字块,渠坡顶和底各现浇一道0.4m×0.3m的C20砼框格梁,渠道每隔20m现浇一道0.4m×0.3m的砼加强带,以保证铺砌的工字块具有足够的牢固性和稳定性。渠底现浇厚0.1m的C20砼护底。
2.4 6+900-7+000为梯形断面,水深2.2m,底宽7m,采用矩形断面重力挡土墙型式,边墙顶宽0.4m,底宽1.2m,为M7.5乱石填腹,M10方块石镶面,方块石厚0.20m,现浇0.15m×0.4m的C20砼压顶,现浇厚0.12mmC20砼护底。
3. 效益分析
干渠实现防渗后,干渠水的利用系数由原来的0.35提高到0.67,年可实现节水600万m3。防止了杂草生长及淤积,节省了人力物力。减少了水的渗漏损失,从而降低了灌溉水的成本,灌溉水成本由0.35元/ m3降低到0.23元/ m3。有效地防止渠道冲刷、淤积、坍塌。
由于灌区续建配套工程采用了经济效益较高的节水模式,增强了广大农民的节水意识,为全市农业推广普及节水型灌溉打下良好的社会基础并起到示范作用。
总之,因地制宜,实现灌区渠道防渗,延长了渠道的寿命,具有显著的经济效益、社会效益和生态环境效益。
[文章编号]1619-2737(2015)12-20-356
[作者简介] 刘锋吉(1964-),男,职称:工程师,工作单位:莱西市水利局。
【关键词】渠道防渗;节水灌溉
【Abstract】Irrigation production area of 23,300 Chicago hm2, is a large-scale irrigation, is the largest agricultural irrigation district of Qingdao City, is the most important city of Lacey agricultural production base. The irrigation construction in the 1960s, has since built and played a lot of irrigation efficiency, the Lacey City of agricultural and rural economic development has made great contributions. However, due to disrepair, engineering is aging and degradation, agricultural irrigation efficiency has been greatly affected. Implementation of the Chicago production and water-saving irrigation area renovation project, you can optimize production Chi irrigation water allocation, greatly improve the utilization of irrigation water, Irrigation expansion and improvement of irrigation efficiency into full play area.
【Key words】Channel seepage;Water-saving irrigation
1.工程概况
产芝水库总库容4.02亿m3,兴利库容1.76亿m3,灌区灌溉面积2.33万hm2,是青岛市最大的农业灌区,也是莱西市最重要的农业生产基地。产芝灌区兴建于60年代,自建成开灌以来,发挥了很大的灌溉效益,为莱西市的农业及农村经济发展做出了巨大贡献。但由于年久失修,工程严重老化,效益逐渐减退,严重制约了农业和农村经济的发展,总干渠又是产芝灌区最重要的输水干渠,因渠系年久老化失修,毁损严重,致使输水能力大大降低,灌溉周期延长,原设计过水能力16.1m3/s,由于渠道属土渠或风化岩,渗漏严重,现状实际过水能力仅为7.6m3/s。灌区灌溉周期设计为15d,现状实际需要30d,干渠水有效利用系数设计为0.78,1979年、1991年、1995年逐年锐减为0.65、0.59、0.45;原综合毛灌溉定额每亩为437m3,工程实施后毛灌溉定额每亩降低为287 m3;设计灌溉面积中现状仅能保灌1万hm2。灌区已经到了“有水放不下去,有水不能浇地”的状况,1998年经水利部立项批准,至2010年底,已实施完成了产芝灌区续建配套与节水改造1~10期工程。
2. 渠道防渗技术措施
按照工程规划,实施完成的产芝灌区配套三期(总干渠)工程,在工程多种防渗型式中,最具有代表性,主要内容为总干渠渠道防渗7Km,配套渠系建筑物48座,总干渠设计流量16.1 m3/s,加大流量19.3m3/s,比降为1/4000,当取不同断面时,设计水深如表1。
从表2可以看出,土工复合膜作防渗层,表面采用砼块作保护层是最佳方案。
根据渠道现在形状,总干渠采取了以下几种防渗措施:
2.1 0+000-0+150、3+350-1+150为梯形断面是大挖方段,且多为石方,水深2.0m,底宽9m,坡比为1:1-1:1.5。2+450-3+800为梯形断面,水深2.0m,底宽8m,且为筑方段,坡比为1:1,土质为砾石土,渗漏严重。采用乱石填腹、M15水泥砂浆砌预制C20砼板镶面,现浇砼护底的护砌形式。砌厚0.25m的M7.5块石填腹,外镶0.06m的C20砼板,现浇0.15×0.40的C20砼压顶,并现浇厚0.12m的C20砼护底。
2.2 0+150-0+350、1+150-2+450、6+510-6+900为矩形断面,底宽9-12米,边墙高2.5-3.0m已浆砌,采取对原渠道砌石脱落危险段局部拆除维修,并对原墙体进行勾缝处理,现浇0.15×0.40m的C20砼压顶,现浇厚0.10m的C20砼护底。
2.3 3+800-6+530为梯形断面,水深2.0m,底宽8m,土质较好,为半挖半填和挖方段。采用土工复合膜衬砌、砼工字块护坡、砼护底护砌型式。渠道整平夯实后坡比达到1:1.0,再铺土工复合膜,土工膜上衬砌厚0.08m的C25砼预制工字块,渠坡顶和底各现浇一道0.4m×0.3m的C20砼框格梁,渠道每隔20m现浇一道0.4m×0.3m的砼加强带,以保证铺砌的工字块具有足够的牢固性和稳定性。渠底现浇厚0.1m的C20砼护底。
2.4 6+900-7+000为梯形断面,水深2.2m,底宽7m,采用矩形断面重力挡土墙型式,边墙顶宽0.4m,底宽1.2m,为M7.5乱石填腹,M10方块石镶面,方块石厚0.20m,现浇0.15m×0.4m的C20砼压顶,现浇厚0.12mmC20砼护底。
3. 效益分析
干渠实现防渗后,干渠水的利用系数由原来的0.35提高到0.67,年可实现节水600万m3。防止了杂草生长及淤积,节省了人力物力。减少了水的渗漏损失,从而降低了灌溉水的成本,灌溉水成本由0.35元/ m3降低到0.23元/ m3。有效地防止渠道冲刷、淤积、坍塌。
由于灌区续建配套工程采用了经济效益较高的节水模式,增强了广大农民的节水意识,为全市农业推广普及节水型灌溉打下良好的社会基础并起到示范作用。
总之,因地制宜,实现灌区渠道防渗,延长了渠道的寿命,具有显著的经济效益、社会效益和生态环境效益。
[文章编号]1619-2737(2015)12-20-356
[作者简介] 刘锋吉(1964-),男,职称:工程师,工作单位:莱西市水利局。