焦郑高速公路:进入冲刺阶段截至2002年3月底,焦郑高速公路已累积完成投资10.72亿元,占预算投资12.16亿元的88.22%。塔南路以东至107国道43.6公里已于7月23日建成通车,工程质量被评定为优良。自开通至今,焦郑高速公路塔南路以东段4个收费站日收入已达16万元以上。塔南路以西12.2公里的路基工程主体己全面完成,并通过指挥部的检查验收。焦郑高速公路焦作南武陟及小徐岗三座收费站办公楼的主体工程已完成。焦作东收费站,武陟服务区办公楼的施工正在紧张进行。
Jiaozheng Expressway: entering the sprint stage As of the end of March 2002, Jiaozheng Expressway has accumulated a total investment of 1.072 billion yuan, accounting for 88.22% of the estimated investment of 1.126 billion yuan. On the east side of Tanan Road, 43.6 kilometers from 107 National Highway was opened to traffic on July 23, and the project quality was assessed as excellent. Since its opening to date, the toll income of four toll stations on the east section of Tarong Expressway has reached 160,000 yuan. The main subgrade project of 12.2 km to the west of Tower Road has been fully completed and has been checked and accepted by the headquarters. Jiaozheng Expressway Jiaozuo South Wuyi and small Xu Gang three main toll station office building has been completed. Jiaozuo East toll station, Wu Mi service area office building construction is intense.