3月21日,中材节能承接的巴基斯坦Maple Leaf40兆瓦燃煤自备电站项目完成里程碑式节点工作——汽轮机一次扣缸成功。这标志着机组本体安装顺利结束,为电站投入运行奠定了坚实的基础。该项目位于巴基斯坦旁遮省Mianwali地区,紧邻中巴经济走廊主要通道,是中材节能在巴基斯坦承建的装机容量和单机容量最大的电站。项目施工过程中,汽轮机扣缸是设备安装中最为重要、最为复杂的工作,也是整个电站的里程碑节点。该环节对施工技
March 21, Sinoma Pakistan’s Maple Leaf coal-fired power plant undertaken by Pakistan to complete the landmark node work - a steam cylinder buckle success. This marks the successful conclusion of the installation of the unit, laying a solid foundation for the operation of the power station. The project is located in the Mianwali area, Phnom Penh, Pakistan. It is close to the main corridor of the China-Pakistan Economic Corridor and is the largest installed capacity and largest stand-alone power plant constructed by Sinoma Energy Conservation in Pakistan. During the construction of the project, the steam turbine buckle cylinder is the most important and complicated work in equipment installation, and is also the milestone node of the entire power plant. The link on the construction technology