摘要:近些年来,随着国家建筑行业高速地改进,越来越多的建筑工程项目的完成,电气安装的质量问题也越来越引起大家注意,引起用户的不满及投诉也时有发生。本文重点结合了作者多年实践中的经验。粗略谈谈下在该方面的一些浅见,提出了个人经验中预防措施。仅供于同行参考。
关键词:建筑工程;电气安装;质量;分析
Abstract: In recent years, along with the national construction industry improving at high speed, more and more of the building project are completed, electrical installation quality problems caused by more and more people pay attention to, because the user discontent and complaint also happen from time to tome. Combined with many years of practical experience. Rough in the aspects of the talk about some shallow view, this paper puts forward the prevention measures in personal experience.
Key Words: building engineering; electrical installation; quality; analysis
中图分类号:S972.7+4 文献标识码:A 文章编号:
1 建筑电气施工的若干质量问题分析
房建室内电气设备的安装质量问题,主要可分为三个方面:箱盒问题,线管问题,电线电缆问题;箱盒主要包括开关箱、电表箱、开关插座盒、接线盒、照明灯具盒等;线管指电线电缆保护管,主要有镀锌电线管,镀锌钢管,PVC 管等;电线电缆主要指进户供电电缆及各部分的供电线,如YJV5 6、BV2.5 等类型。
1.1 箱盒问题室内箱盒的安装是室内电气安装的重要环节,直接影响了最终室内的美观程度,从技术角度来说并未有技术难度较大的地方,但是问题时有发生,应该引起充分重视。
1.1.1 安装标高不一致,箱盒移位。规范要求,同一室内的电源、电话、电视等插座面板应在同一水平标高上,高差应小于5mm;同一室内的照明开关要按图纸要求布置在同一水平标高上,高差也应小于5mm。电表箱、配电箱要安装到位,不得倾斜。如果安装箱盒或者木模时没有控制好水平标高,或者土建施工时现浇混凝土模板变形移动,导致箱盒移位,致使箱盒倾斜或凹进墙面等等,这些情况发生,最终致使成品歪斜,高低不一,严重影响美观。
1.1.2 开孔不整齐,箱盒变形。线管进箱盒时,预留孔洞可能不适用,施工时就用电、气焊切割开孔,或者用钢锯锯成长方孔,甚至敲掉一块箱子板,致使箱盒变形,孔径不规矩。因此,要求首先尽量使用箱盒的预留孔洞。必须开孔时,要使用开孔钻等专用工具,并做好新开孔的防腐处理,面漆要与原来颜色一致。
1.2 线管问题线缆保护管的敷设一般均为暗敷,要严格按设计图纸及相应技术规范敷设,不能随意布置,避免室内装修时由于墙上打孔损坏线管。
1.2.1 管内渗漏。预设在混凝土楼板内的线管,接口处渗漏是最常见的质量问题,因为接口处未加套管,或承插口做的过短,粘合剂不完全,仅用黑胶布或塑料带包缠一下,没有按照工艺规定操作,有时漏进水泥砂浆,干涸后堵塞线管,造成后续穿线无法进行。
1.2.2 管口问题。金属管口有毛刺及管口入箱、盒长度不齐是管口问题中的典型。管口有毛刺是由于锯管后未用挫刀光口,管口毛刺在穿线时极易损伤线缆绝缘层,造成绝缘测试时不能成功。线管进入箱盒长度不一致,是因为管口入箱、盒后受力出現负值或者管口没有固定。大模板现浇混凝土板墙内配管时,盒子内有管口脱掉,造成剔凿混凝土墙再找管口的后果。
1.3 电线电缆问题电线电缆的敷设是电气安装施工的重要环节,由于电线电缆一般跨度较长,环节较多,又加上其质量问题一般都很隐蔽,出现质量问题很难查找,因而做好预防措施显得十分必要。
1.3.1 导线绝缘层损伤。规范要求,导线间和导线对地间电阻必须大于0.5MΩ。在施工中,穿线前放线时,将整盘线往外抽拉,引起螺旋形圈集中,出现背扣或死扣,损伤绝缘层。管内穿线前漏戴护口,拉线过程中毛刺划伤绝缘层。为避免这类质量问题,要求在穿线之前应严格戴好护口,管口无丝扣的可戴塑料内护口。放线时应用放线车,将整盘导线放在线盘上,并在线轴上做出记号,自然转动线轴放出导线,避免出现螺圈,防止绝缘层受损。
1.3.2 导线芯损伤。导线芯线损伤,造成额定通过电流降低,导线在受损处发热,易导致事故发生。一般发生在除绝缘层时,刀刃直角割断导线绝缘层,切伤了芯线。也有导线在搬运敷设过程中受到重物倾轧,使芯线受损。所以在剥切导线塑料绝缘层时,应采用专用剥线钳。剥切橡胶绝缘层时,刀刃禁忌直角切割,要以斜角剥切。对导线芯线被削伤的,应将已削伤的线头剪掉一段,重新削头、接头。在搬运敷设过程中,要加强防护,避免损伤芯线。
1.3.3 导线接头不规范。有些电气线路过长,在操作时会有一些接头产生,对接头的打线、绝缘及防潮处理不好,就会产生接触不良问题,甚至发生断路、短路等现象。穿入配管导线的接头应设在接线盒内,出现问题易于解决,接头搭接应牢固,做好绝缘防潮处理。导线连接时本身自缠不应少于五圈,可有效降低接触电阻,导线接头接触电阻超过限度时,应再增加接触面或重新接头测定。对于铜、铝线连接,须做过渡段处理或采用铜铝过渡端子压接。多股导线连接设备、器具时须使用接线端子并设防松弹簧垫圈。
1.3.4 零相线不合规范问题。对于TN-S 系统,相线和零线若使用同一颜色的导线不易区别,而且断线、留头时没有严格做出记号,以致相线和零线混淆不清,致使安全设备无法正常运行,易于发生触电事故,造成人员伤害。为了保证相线、零线不混淆,必须采用不同颜色的塑料线。统一用浅蓝色及在放线车的线轴上做出记号,以保证做到相线和零线严格区分。
对于安装电源插座,面向插座的左侧应接零线(N),右侧应接相线(L),中间上方应接保护地线(PE)。
1.4 其他问题电线管与暖气、热水、煤气管之间的平行距离不应小于300mm,交叉距离不应小于100mm,施工中必须充分注意。
对于强电网络和弱电网络的敷设问题,应该分开走线,必须一同走线时,要做好屏蔽处理。线管在楼板及地坪内无垫层敷设时,容易产生裂缝,需要保证20mm 以上的素混凝土保护层,以防止产生裂缝。
在 24 砖墙或混凝土墙内暗装铁木配电箱,因墙体比较窄,配电箱背后保护层过薄,抹灰层不粘结,易出现裂缝。因此要求箱体背面钉钢板网,而后抹灰,避免墙面出现裂缝。
2 结束语
以上只是笔者对部分电气装置施工控制的一些浅见,还有许多内容未能涉及。建筑施工中室内电气设备的安装工作,由于施工细节较多,易出现各种质量问题,因此,只有认真理解和执行规范,结合工程实际,找出各种质量问题的成因,在施工前做好充分的技术交底,有针对性的制定技术方案,才能使电气装置安装工程的质量控制得到完善,从而有效提高施工安装质量,提高施工效率,完成合格建筑产品。
关键词:建筑工程;电气安装;质量;分析
Abstract: In recent years, along with the national construction industry improving at high speed, more and more of the building project are completed, electrical installation quality problems caused by more and more people pay attention to, because the user discontent and complaint also happen from time to tome. Combined with many years of practical experience. Rough in the aspects of the talk about some shallow view, this paper puts forward the prevention measures in personal experience.
Key Words: building engineering; electrical installation; quality; analysis
中图分类号:S972.7+4 文献标识码:A 文章编号:
1 建筑电气施工的若干质量问题分析
房建室内电气设备的安装质量问题,主要可分为三个方面:箱盒问题,线管问题,电线电缆问题;箱盒主要包括开关箱、电表箱、开关插座盒、接线盒、照明灯具盒等;线管指电线电缆保护管,主要有镀锌电线管,镀锌钢管,PVC 管等;电线电缆主要指进户供电电缆及各部分的供电线,如YJV5 6、BV2.5 等类型。
1.1 箱盒问题室内箱盒的安装是室内电气安装的重要环节,直接影响了最终室内的美观程度,从技术角度来说并未有技术难度较大的地方,但是问题时有发生,应该引起充分重视。
1.1.1 安装标高不一致,箱盒移位。规范要求,同一室内的电源、电话、电视等插座面板应在同一水平标高上,高差应小于5mm;同一室内的照明开关要按图纸要求布置在同一水平标高上,高差也应小于5mm。电表箱、配电箱要安装到位,不得倾斜。如果安装箱盒或者木模时没有控制好水平标高,或者土建施工时现浇混凝土模板变形移动,导致箱盒移位,致使箱盒倾斜或凹进墙面等等,这些情况发生,最终致使成品歪斜,高低不一,严重影响美观。
1.1.2 开孔不整齐,箱盒变形。线管进箱盒时,预留孔洞可能不适用,施工时就用电、气焊切割开孔,或者用钢锯锯成长方孔,甚至敲掉一块箱子板,致使箱盒变形,孔径不规矩。因此,要求首先尽量使用箱盒的预留孔洞。必须开孔时,要使用开孔钻等专用工具,并做好新开孔的防腐处理,面漆要与原来颜色一致。
1.2 线管问题线缆保护管的敷设一般均为暗敷,要严格按设计图纸及相应技术规范敷设,不能随意布置,避免室内装修时由于墙上打孔损坏线管。
1.2.1 管内渗漏。预设在混凝土楼板内的线管,接口处渗漏是最常见的质量问题,因为接口处未加套管,或承插口做的过短,粘合剂不完全,仅用黑胶布或塑料带包缠一下,没有按照工艺规定操作,有时漏进水泥砂浆,干涸后堵塞线管,造成后续穿线无法进行。
1.2.2 管口问题。金属管口有毛刺及管口入箱、盒长度不齐是管口问题中的典型。管口有毛刺是由于锯管后未用挫刀光口,管口毛刺在穿线时极易损伤线缆绝缘层,造成绝缘测试时不能成功。线管进入箱盒长度不一致,是因为管口入箱、盒后受力出現负值或者管口没有固定。大模板现浇混凝土板墙内配管时,盒子内有管口脱掉,造成剔凿混凝土墙再找管口的后果。
1.3 电线电缆问题电线电缆的敷设是电气安装施工的重要环节,由于电线电缆一般跨度较长,环节较多,又加上其质量问题一般都很隐蔽,出现质量问题很难查找,因而做好预防措施显得十分必要。
1.3.1 导线绝缘层损伤。规范要求,导线间和导线对地间电阻必须大于0.5MΩ。在施工中,穿线前放线时,将整盘线往外抽拉,引起螺旋形圈集中,出现背扣或死扣,损伤绝缘层。管内穿线前漏戴护口,拉线过程中毛刺划伤绝缘层。为避免这类质量问题,要求在穿线之前应严格戴好护口,管口无丝扣的可戴塑料内护口。放线时应用放线车,将整盘导线放在线盘上,并在线轴上做出记号,自然转动线轴放出导线,避免出现螺圈,防止绝缘层受损。
1.3.2 导线芯损伤。导线芯线损伤,造成额定通过电流降低,导线在受损处发热,易导致事故发生。一般发生在除绝缘层时,刀刃直角割断导线绝缘层,切伤了芯线。也有导线在搬运敷设过程中受到重物倾轧,使芯线受损。所以在剥切导线塑料绝缘层时,应采用专用剥线钳。剥切橡胶绝缘层时,刀刃禁忌直角切割,要以斜角剥切。对导线芯线被削伤的,应将已削伤的线头剪掉一段,重新削头、接头。在搬运敷设过程中,要加强防护,避免损伤芯线。
1.3.3 导线接头不规范。有些电气线路过长,在操作时会有一些接头产生,对接头的打线、绝缘及防潮处理不好,就会产生接触不良问题,甚至发生断路、短路等现象。穿入配管导线的接头应设在接线盒内,出现问题易于解决,接头搭接应牢固,做好绝缘防潮处理。导线连接时本身自缠不应少于五圈,可有效降低接触电阻,导线接头接触电阻超过限度时,应再增加接触面或重新接头测定。对于铜、铝线连接,须做过渡段处理或采用铜铝过渡端子压接。多股导线连接设备、器具时须使用接线端子并设防松弹簧垫圈。
1.3.4 零相线不合规范问题。对于TN-S 系统,相线和零线若使用同一颜色的导线不易区别,而且断线、留头时没有严格做出记号,以致相线和零线混淆不清,致使安全设备无法正常运行,易于发生触电事故,造成人员伤害。为了保证相线、零线不混淆,必须采用不同颜色的塑料线。统一用浅蓝色及在放线车的线轴上做出记号,以保证做到相线和零线严格区分。
对于安装电源插座,面向插座的左侧应接零线(N),右侧应接相线(L),中间上方应接保护地线(PE)。
1.4 其他问题电线管与暖气、热水、煤气管之间的平行距离不应小于300mm,交叉距离不应小于100mm,施工中必须充分注意。
对于强电网络和弱电网络的敷设问题,应该分开走线,必须一同走线时,要做好屏蔽处理。线管在楼板及地坪内无垫层敷设时,容易产生裂缝,需要保证20mm 以上的素混凝土保护层,以防止产生裂缝。
在 24 砖墙或混凝土墙内暗装铁木配电箱,因墙体比较窄,配电箱背后保护层过薄,抹灰层不粘结,易出现裂缝。因此要求箱体背面钉钢板网,而后抹灰,避免墙面出现裂缝。
2 结束语
以上只是笔者对部分电气装置施工控制的一些浅见,还有许多内容未能涉及。建筑施工中室内电气设备的安装工作,由于施工细节较多,易出现各种质量问题,因此,只有认真理解和执行规范,结合工程实际,找出各种质量问题的成因,在施工前做好充分的技术交底,有针对性的制定技术方案,才能使电气装置安装工程的质量控制得到完善,从而有效提高施工安装质量,提高施工效率,完成合格建筑产品。