我处302队在林南仓矿西一采区运输机下山施工中,从开工以来连续几个月都取得了较好成绩。第一个月完成了72.6米,第二个月完成了100.7米,特别在五月份第三个月中完成了成巷203.2米,而且各项技术经济指标也完成得比较好。如:效率定额为0.74米/工·日,实际为1.46米/工·日;成本预算为32.56万元,实际为20.74万元;火药消耗定额为11.88公斤/米,实际为10.75公斤/米;木材消耗定额为0.48米~3/米,实际为0.23米~3/米。工程质量经矿务局、公司、处三级联合验收定为优良,安全上全月无事故,设备完
I Division 302 team in Linnan warehouse West mining area downhill transport construction, from the start for several months have achieved good results. 72.6 meters completed in the first month, 100.7 meters completed in the second month, 203.2 meters completed in the third month of May in particular, and various technical and economic indicators have also been completed. Such as: the efficiency of 0.74 m / day, the actual 1.46 m / day, the cost budget of 325,600 yuan, the actual 207,400 yuan; gunpowder consumption of 11.88 kg / m, the actual 10.75 kg / m; Wood consumption quota is 0.48 m ~ 3 / m, actually 0.23 m ~ 3 / m. The quality of the project by the Bureau of Mines, the company, at the three joint acceptance as fine, no accidents on the safety of the entire equipment