铁川桥水电站引水隧洞上平段、斜井及调压井衬砌混凝土现场实际施工表明,6条施工支洞确保了引水隧洞各部位混凝土浇筑,工期可满足进度计划要求;采用自制钢模台车进行洞内衬砌混凝土浇筑操作简单灵活,每个工作面混凝土衬砌进度可保证60 m/月以上;调压井及斜井施工改用人工搭设脚手架,斜井衬砌浇筑采用混凝土泵机,调压井设置吊篮、衬砌混凝土采用高压地泵输送等施工方法,可满足衬砌混凝土浇筑进度和质量等要求:建议斜井上弯段和下弯段衬砌混凝土的异形模板采用定制钢模施工。
The actual construction of the lining of the upper section of the diversion tunnel, inclined shaft and surge shaft of Tiechuanqiao Hydropower Station shows that the six construction branch holes ensure the concrete pouring in all parts of the diversion tunnel and the construction period can meet the requirements of the schedule. The self-made steel mold trolley The pouring of concrete lining in the tunnel is simple and flexible. The progress of concrete lining of each working face can be guaranteed to be 60 m / month or more. Manual surge scaffolding is to be used in surge shaft and inclined shaft construction. Concrete pump is used to pour in inclined shaft lining. The construction method of setting basket and lining concrete with high-pressure pump can meet the requirements of the progress and quality of lining concrete pouring. It is suggested that the special-shaped steel formwork should be used for the special-shaped formwork of the liner concrete in the upper and lower bending sections of inclined shafts.