立井施工超过一定深度后,需开凿转水站硐室(腰泵房)安装转水泵排水。对于直径较大、涌水量较小的井筒,可在井筒内适当位置安一个固定盘作为转水盘,在盘上安泵转排水,较之开腰泵房能缩短井筒施工工期约15~20天,节约开凿转水站峒室的投资约1万元。我处先后在徐家楼新井、荆各庄主井和副井、范各庄新井及钱家营副井采用过转水盘排水。均取得了安全可靠、经济合理的良好效果。
Shaft construction more than a certain depth, the need to dig the water transfer station chamber (lumbar pump room) to install the pump drainage. For larger diameter and smaller water volume wellbores, a fixed pan may be installed in the wellbore as a pan for pumping and draining water on the pan, which will shorten the construction period of the wellbore by about 15-20 Day, save turning water station 峒 room investment of about 10,000 yuan. I have offices in the new Xujiaoling, Jingge Zhuang main shaft and auxiliary shaft, Fangezhuang new wells and Qian Jiaying auxiliary wells have been used to divert water tray drainage. Have achieved a safe, reliable, economical and reasonable good results.