立井施工使用转水盘排水

来源 :建井技术 | 被引量 : 0次 | 上传用户:gumozaoshi
下载到本地 , 更方便阅读
声明 : 本文档内容版权归属内容提供方 , 如果您对本文有版权争议 , 可与客服联系进行内容授权或下架
论文部分内容阅读
立井施工超过一定深度后,需开凿转水站硐室(腰泵房)安装转水泵排水。对于直径较大、涌水量较小的井筒,可在井筒内适当位置安一个固定盘作为转水盘,在盘上安泵转排水,较之开腰泵房能缩短井筒施工工期约15~20天,节约开凿转水站峒室的投资约1万元。我处先后在徐家楼新井、荆各庄主井和副井、范各庄新井及钱家营副井采用过转水盘排水。均取得了安全可靠、经济合理的良好效果。 Shaft construction more than a certain depth, the need to dig the water transfer station chamber (lumbar pump room) to install the pump drainage. For larger diameter and smaller water volume wellbores, a fixed pan may be installed in the wellbore as a pan for pumping and draining water on the pan, which will shorten the construction period of the wellbore by about 15-20 Day, save turning water station 峒 room investment of about 10,000 yuan. I have offices in the new Xujiaoling, Jingge Zhuang main shaft and auxiliary shaft, Fangezhuang new wells and Qian Jiaying auxiliary wells have been used to divert water tray drainage. Have achieved a safe, reliable, economical and reasonable good results.
其他文献
中国广电集团产业结构严重失调周葆华、刘芊芊在2003年第7期《中国广播电视学刊》以上海文广集团为个案,分析中国广电集团发展的空间。文章认为,跟国外著名的传媒集团比较,
请下载后查看,本文暂不支持在线获取查看简介。 Please download to view, this article does not support online access to view profile.
2003年10月24日,国家广电总局全国有线广播电视监测网签约仪式在北京工会大楼隆重举行。由此,有线广播电视监测网项目进入了第三、四期阶段。 广电总局广播电视监测中心总工
夹河煤矿洗煤厂原设计入洗能力为60万吨/年,近几年来经过技术改造,实现了跳汰机单机自动化,浮选工艺参数自动调节,全厂集中控制。入洗原煤能力逐年增长,1980年以来一直稳定
从1979年开始,曾家山一井矿井由浅部逐步转入深部开采.同时,计划产量超设计能力,采掘工作面增加,由于矿井通风能力不足,风量日趋紧张,安全受到威胁,被迫 Starting from 1979
2003年g月广告收入前20名的行业媒体排名媒体名称广告收人(万元)1中国经营报1 961 .802中国贸易报1 375 773安徽市场报1 197.914瑞丽服饰美容959 .705中国企业报708 .356科学
据国外报道,自从1990年美国修改通信法以来,美国的CATV业者积极开拓通信市场。对于广播、声音、数据的“全服务”,业者是如何展开经营战略的?这正是业界关心的重要视点。现
辽宁省地矿局第五地质大队,是一个有800名职工、开动六台钻机进行固体矿产普查勘探的综合地质大队.设有四个地质分队,四个钻探井队,三个劳务单位(车间、车队、化验室)和劳动
目的 对 B期非小细胞肺癌 (NSCL C)化放疗后手术临床疗效的评价。方法 对 42例 B期非小细胞肺癌的诊断建立在较全面的分期检查和剖胸探查术的基础上 ,前期治疗包括 2个周
当人们面临每年需把大约350万吨矿石从矿区运到精炼厂,其运距达51公里的问题时,大多数人会考虑用铁路是最好的方案,或者采用特大吨位的专用卡车。但是,Worsley Alumina pty.