天荒坪抽水蓄能电站1号上游输水系统是我国目前水头最高的大直径水工隧洞,一洞三机式布置,承受的最大静水头为680m,充水分7个阶段进行,第1~第5阶段充水速率为10m/h,第6、7阶段各分2个小台阶,充水速率为5m/h。排水分3个阶段,采用压力表和压力变送器共同监测水道内水压力。由于采取的充排水程序合理、措施得当,充排水试验获得了成功,水道设计、施工、安装质量经受住了初步考验。
Tianhuangping Pumped Storage Power Station No. 1 upstream water delivery system is China’s current head of the largest diameter hydraulic tunnel, a hole three-machine layout, the maximum static head to withstand 680m, filled with water at seven stages, The 5th stage water-filling rate is 10m / h, the 6th and 7th stages are divided into 2 small steps, and the water-filling rate is 5m / h. Drainage in three stages, the use of pressure gauges and pressure transmitters together to monitor water pressure within the channel. Due to the reasonable filling and draining procedures, the proper measures and the successful drainage and drainage tests, the water channel design, construction and installation quality have withstood the initial test.