一、概述石臼港外海深水波要素是利用二十五年历史天气图推算而得,然后经过折射及浅水计算得到码头前沿12米水深处的五十年一遇的设计波要素,即H_1%=7.1米,T=14.2秒,但在10米等深线以内,水下地形异常复杂,水下沙坝、瞧石较多,复杂的等深线已无法进行较准确的折射计算,所以护岸处的设计波要素在当时只能考虑浅水的影响进行估算而得。为了验证该取值的可靠性,自1981年4月至1982年3月于石臼港海区拟建码头、护岸附近共设了五个测波点进行波浪观测,即1号点水深17.5米,采
I. Outline The deep-water wave element of Shijiugang Port is derived from the historical weather map of 25 years and then is subjected to 50-year-long design wave elements at a water depth of 12 meters at the front of the quay through refraction and shallow water calculation. That is, H_1% 7.1 meters and T = 14.2 seconds. However, within the isobath of 10 meters, the underwater terrain is extremely complicated. The underwater sand bar and stone look more complicated complicated isobaths have been unable to calculate the refraction accurately. Therefore, The design wave elements were only estimated at the time considering the effects of shallow water. In order to verify the reliability of this value, from April 1981 to March 1982 in Shijiakang Harbor proposed wharf, a total of five wave points near the revetment wave observation, that point 1 point depth of 17.5 meters, mining