在传统三通支管翻边制造工艺的基础上,研究了核电站用超级管道管嘴的热挤压成形工艺。对超级管道管嘴的成形预制孔开孔尺寸、顶头(凸模)相关结构尺寸进行不同挤压工艺方案设计,并进行大量的管嘴热挤压成形工艺试验,获得了管嘴成形最佳关键工艺参数。试验结果表明:管嘴的预制孔直径可以按照体积不变的原则进行计算;顶头与凹模之间的间隙是决定管嘴壁厚的关键因素,管嘴壁厚约为间隙的92%~96%。通过理论计算可以估算管嘴成形高度,计算偏差一般在±10%以内。
On the basis of the manufacturing process of the traditional three-way branch pipe burring, the hot extrusion forming process of the super-pipe nozzle for nuclear power station was studied. The design of different extrusion process schemes for the size of preformed hole, the size of the head (punch) of the super-shaped pipe nozzle and the hot extrusion process of the nozzle were studied, and the best key for nozzle forming was obtained Process parameters. The test results show that the nozzle pre-hole diameter can be calculated in accordance with the principle of constant volume; the gap between the head and the die is to determine the nozzle wall thickness of the key factors, the nozzle wall thickness of about 92% ~ 96 %. Through the theoretical calculation can estimate nozzle forming height, the calculation deviation is generally within ± 10%.