论文部分内容阅读
【摘 要】高层建筑的沉降观测技术的要求,根据工程的特点布局、现场的环境条件制订测量施测方案,由建设单位提供的水准控制点(或城市精密导线点)根据工程的测量施测方案和布网原则的要求建立水准控制网。
【关键词】沉降;观测
Settlement observation technology of high-rise building
Xi Jun-feng,Xiao Jian-ming
(Taixing Zhongxing Construction Quality Testing Center Co., Ltd Taixing Jiangsu 225400)
【Abstract】High-rise building requirements of the settlement of observation techniques, based on the engineering characteristics of the layout, on-site measurements of environmental conditions for development of Surveying program provided by the standard construction unit control point (or city precision wire points) According to the measurement of Surveying Engineering program and distribution network principles requires the establishment of standard control network.
【Key words】Settlement;Observation
1. 沉降观测的基本要求
1.1 仪器设备、人员素质的要求。
根据沉降观测精度要求高的特点,为能精确地反映出建构筑物在不断加荷作下的沉降情况,一般规定测量的误差应小于变形值的1/10~1/20,为此要求沉降观测应使用精密水准仪(S1或S05级),水准尺也应使用受环境及温差变化影肉小的高精度铟合金水准尺。在不具备铟合金水准尺的情况下,使用一般塔尺尽量使用第一段标尺。
人员素质的要求,必须接受专业学习及技能培训,熟练掌握仪器的操作规程,熟悉测量理论能针对不同工程特点、具体情况采用不同的观测方法及观测程序,对实施过程中出现的问题能够会分析原因并正确的运用误差理论进行平差计算,做到按时、快速、精确地完成每次观测任务。
1.2 观测时间的要求。
建构筑物的沉降观测对时间有严格的限制条件,特别是首次观测必须按时进行,否则沉降观测得不到原始数据,而是整个观测得不到完整的观测意义。其他各阶段的复测,根据工程进展情况必须定时进行,不得漏测或补测。只有这样,才能得到准确的沉降情况或规律。相邻的两次时间间隔称为一个观测周期,一般高层建筑物的沉降观测按一定的时间段为一观测周期(如:次/30天)或按建筑物的加荷情况每升高一层(或数层)为一观测周期,无论采取何种方式都必须按施测方案中规定的观测周期准时进行。
1.3 观测点的要求。
为了能够反映出建构筑物的准确沉降情况,沉降观测点要埋设在最能反映沉降特征且便于观测的位置。一般要求建筑物上设置的沉降观测点纵横向要对称,且相邻点之间间距以15~30米为宜,均匀地分布在建筑物的周围。通常情况下,建筑物设计图纸上有专门的沉降观测点布置图。
再就是,埋设的沉降观测点要符合各施工阶段的观测要求,特别要考虑到装修装饰阶段因墙或柱饰面施工而破坏或掩盖住观测点,不能连续观测而失去观测意义。
1.4 沉降观测的自始至终要遵循“五定”原则。
所谓“五定”,即通常所说的沉降观测依据的基准点、工作基点和被观测物上的沉降观测点,点位要稳定;所用仪器、设备要稳定;观测人员要稳定;观测时的环境条件基本一致;观测路线、镜位、程序和方法要固定。以上措施在客观上尽量减少观测误差的不定性,使所测的结果具有统一的趋向性,保证各次复测结果与首次观测的结果可比性更一致,使所观测的沉降量更真实。
1.5施测要求。
仪器、设备的操作方法与观测程序要熟悉、正确。在首次观测前要对所用仪器的各项指标进行检测校正,必要时经计量单位予以鉴定。连续使用3~6个月重新对所用仪器、设备进行检校。
在观测过程中,操作人员要相互配合,工作协调一致,认真仔细,做到步步有校核。
1.6 沉降观测精度的要求。
根据建筑物的特性和建设、设计单位的要求选择沉降观测精度的等级。再未有特除要求情况下,一般性的高层建构筑物施工过程中,采用二等水准测量的观测方法就能满足沉降观测的要求。我们在东方大厦的沉降观测检测过程中就采用二等水准测量的观测方法。各项观测指标要求如下:
(1)往返较差 、附和或环线闭合差: △h=∑a-∑b≤1.0n,表示测站数。(或△h=∑a-∑b≤1.0L, L表示观测路线距离)
(2)前后视距: ≤30m
(3)前后视距差: ≤1.0m
(4)前后视距累积差 ≤3.0m
(5)沉降观测点相对于后视点的高差容差 :≤1.0mm
(6)水准仪的精度不低于N2级别
1.7 沉降观测成果整理及计算要求。原始数据要真实可靠,记录计算要符合规范的要求,依据正确,严谨有序,步步校核,结果有效的原则进行成果整理及计算。
2. 具体施测程序及步骤
2.1建立水准控制网。
根据工程的特点布局、现场的环境条件制订测量施测方案,由建设单位提供的水准控制点(或城市精密导线点)根据工程的测量施测方案和布网原则的要求建立水准控制网。要求: (1)一般高层建筑物周围要布置三个以上水准点,水准点的间距不大于100米。
(2)在场区内任何地方架设仪器至少后视到两个水准点,并且场区内各水准点构成闭合图形,以便闭合检校。
(3)各水准点要设在建筑物开挖、地面沉降和震动区范围之外,水准点的埋深要符合二等水准测量的要求(大于1.5米)根据工程特点,建立合理的水准控制网,与基准点联测,平差计算出各水准点的高程。
2.2 建立固定的观测路线。
由场区水准控制网,依据沉降观测点的埋设要求或图纸设计的沉降观测点布点图,确定沉降观测点的位置。在控制点与沉降观测点之间建立固定的观测路线,并在架设仪器站点与转点处作好标记桩,保证各次观测均沿统一路线。
2.3 沉降观测。
根据编制的工程施测方案及确定的观测周期,首次观测应在观测点安稳固后及时进行。一般高层建筑物有一或数层地下结构,首次观测应自基础开始,在基础的纵横轴线上(基础局边)按设计好的位置埋设沉降观测点(临时的),等临时观测点稳固好,进行首次观测。
首次观测的沉降观测点高程值是以后各次观测用以比较的基础,其精度要求非常高,施测时一般用N2或N3级精密水准仪。并且要求每个观测点首次高程应在同期观测两次后决定。
随着结构每升高一层,临时观测点移上一层并进行观测直到十0.00再按规定埋设永久观测点(为便于观测可将永久观测点设于十500mm)。然后每施工一层就复测一次,直至竣工。
2.4 将各次观测记录整理检查无误后,进行平差计算,求出各次每个观测点的高程值。从而确定出沉降量。
某个观测点的每周期沉降量: △c=Hh,I-Hn,I -1 N表示某个观测点,I表示观测周期数(I=1,2,3……)且 H1=H0累计沉降量: △C=∑△ c(n)n表示观测点号。
2.5 统计表汇总
(1)根据各观测周期平差计算的沉降量,列统计表,进行汇总。
(2)绘制各观测点的下沉曲线。
首先建立下沉曲线坐标,横坐标为时间坐标,纵坐标上半部为荷载值,下半部为各沉降观测周期的沉降量。
将统计表中各观测点对应的观测周期所测得沉降量画于坐标中,并将相应的荷载值也画于坐标中,连线,就得到对应于荷载值的沉降曲线。
(3)根据沉降量统计表和沉降曲线图,我们可以预测建筑物的沉降趋势,将建筑物的沉降情况及时的反馈到有关主管部门,正确地指导施工。特别座在沉陷性较大的地基上重要建筑物的不均匀沉降的观测显得更为重要。
利用沉降曲线还可计算出因地基不均匀沉降引起的建筑物倾斜度:q=│△Cm-△Cn│/Lmn,△Cm,△Cn分别为m,n点的总沉降量,Lmn为m,n点的距离。
对沉降观测的成果分析,我们还可以找出同一地区类似结构形式建筑物影响其沉降的主要因素,给施工单位编好施工组织设计正确指导施工大有裨益,同样也为勘察设计单位提供宝贵的一手资料,设计出更完善的施工图纸。
2.6 观测中的注意事项:
(1)严格按测量规范的要求施测。
(2)前后视观测最好用同一水平尺。
(3)各次观测必须按照固定的观测路线进行。
(4)观测时要避免阳光直射,且各观测环境基本一致。
(5)成像清晰、稳定时再读数。
(6)随时观测,随时检核计算,观测时要-气阿成。
(7)在雨季前后要联测,检查水准点的标高是否有变动。
(8)将各次所观测沉降情况及时反馈有关部门,当建筑物每天(24h)连续沉降量超过1mm时应及时的向施工单位和建设单位告知,让施工单位停止施工,会同有关部门采取应急措施。
3.探讨的两个问题
3.1 确定建筑物沉降观测精度的合理性。由于现行规范对施工单位施工过程的沉降观测要求不明朗,这对施工单位在建筑物沉降观测精度选择随意性较大,这就要求检测单位严格把关,提高沉降观测的测量精度,但沉降观测精度选择既不能太高也不能太低,要合理适宜,适合工程特性的需要。既不造成无谓的浪费也要保证观测结果的准确性。这样,本人认为一般高层及重要的建(构)筑物在首次观测过程中适用精密仪器的设备(高级水准仪、铟合金尺等)在±0.00以上部分按二等以上水准测量方法,采用放大率倍数较大的S2或S3水准仪进行观测,也可以测出较理想的结果。
3.2 在沉降观测过程中,沉降量与时问关系曲线不是单边下行光滑曲线,而是起伏状现象。这就分析原因,进行修正。
(1)第二次观测出现回升,而以后各次观测又逐渐下降。可能是首次观测精过低,若回升超过5mm时,第一次观测作废,若回升5mm内,第二次与第一次调整标高一致。 (2)曲线在某点突然回升。
原因:水准点或观测点被碰动所致且水准点碰动后标高低于碰前标高,观测点碰后高于碰前。
处理措施:取相邻另一观测点的相同期间沉降量作为被碰观测点之沉降量。
(3)曲线自某点起渐渐回升。
原因:一般是水准点下沉所致。
措施:确定水准点下沉值,与高级水准点符合测量,确定下沉重。
参考文献
[1] 《工程测量规范》 GB50026-2007.
[2] 《建筑变形测量规范》JGJ8-2007
【关键词】沉降;观测
Settlement observation technology of high-rise building
Xi Jun-feng,Xiao Jian-ming
(Taixing Zhongxing Construction Quality Testing Center Co., Ltd Taixing Jiangsu 225400)
【Abstract】High-rise building requirements of the settlement of observation techniques, based on the engineering characteristics of the layout, on-site measurements of environmental conditions for development of Surveying program provided by the standard construction unit control point (or city precision wire points) According to the measurement of Surveying Engineering program and distribution network principles requires the establishment of standard control network.
【Key words】Settlement;Observation
1. 沉降观测的基本要求
1.1 仪器设备、人员素质的要求。
根据沉降观测精度要求高的特点,为能精确地反映出建构筑物在不断加荷作下的沉降情况,一般规定测量的误差应小于变形值的1/10~1/20,为此要求沉降观测应使用精密水准仪(S1或S05级),水准尺也应使用受环境及温差变化影肉小的高精度铟合金水准尺。在不具备铟合金水准尺的情况下,使用一般塔尺尽量使用第一段标尺。
人员素质的要求,必须接受专业学习及技能培训,熟练掌握仪器的操作规程,熟悉测量理论能针对不同工程特点、具体情况采用不同的观测方法及观测程序,对实施过程中出现的问题能够会分析原因并正确的运用误差理论进行平差计算,做到按时、快速、精确地完成每次观测任务。
1.2 观测时间的要求。
建构筑物的沉降观测对时间有严格的限制条件,特别是首次观测必须按时进行,否则沉降观测得不到原始数据,而是整个观测得不到完整的观测意义。其他各阶段的复测,根据工程进展情况必须定时进行,不得漏测或补测。只有这样,才能得到准确的沉降情况或规律。相邻的两次时间间隔称为一个观测周期,一般高层建筑物的沉降观测按一定的时间段为一观测周期(如:次/30天)或按建筑物的加荷情况每升高一层(或数层)为一观测周期,无论采取何种方式都必须按施测方案中规定的观测周期准时进行。
1.3 观测点的要求。
为了能够反映出建构筑物的准确沉降情况,沉降观测点要埋设在最能反映沉降特征且便于观测的位置。一般要求建筑物上设置的沉降观测点纵横向要对称,且相邻点之间间距以15~30米为宜,均匀地分布在建筑物的周围。通常情况下,建筑物设计图纸上有专门的沉降观测点布置图。
再就是,埋设的沉降观测点要符合各施工阶段的观测要求,特别要考虑到装修装饰阶段因墙或柱饰面施工而破坏或掩盖住观测点,不能连续观测而失去观测意义。
1.4 沉降观测的自始至终要遵循“五定”原则。
所谓“五定”,即通常所说的沉降观测依据的基准点、工作基点和被观测物上的沉降观测点,点位要稳定;所用仪器、设备要稳定;观测人员要稳定;观测时的环境条件基本一致;观测路线、镜位、程序和方法要固定。以上措施在客观上尽量减少观测误差的不定性,使所测的结果具有统一的趋向性,保证各次复测结果与首次观测的结果可比性更一致,使所观测的沉降量更真实。
1.5施测要求。
仪器、设备的操作方法与观测程序要熟悉、正确。在首次观测前要对所用仪器的各项指标进行检测校正,必要时经计量单位予以鉴定。连续使用3~6个月重新对所用仪器、设备进行检校。
在观测过程中,操作人员要相互配合,工作协调一致,认真仔细,做到步步有校核。
1.6 沉降观测精度的要求。
根据建筑物的特性和建设、设计单位的要求选择沉降观测精度的等级。再未有特除要求情况下,一般性的高层建构筑物施工过程中,采用二等水准测量的观测方法就能满足沉降观测的要求。我们在东方大厦的沉降观测检测过程中就采用二等水准测量的观测方法。各项观测指标要求如下:
(1)往返较差 、附和或环线闭合差: △h=∑a-∑b≤1.0n,表示测站数。(或△h=∑a-∑b≤1.0L, L表示观测路线距离)
(2)前后视距: ≤30m
(3)前后视距差: ≤1.0m
(4)前后视距累积差 ≤3.0m
(5)沉降观测点相对于后视点的高差容差 :≤1.0mm
(6)水准仪的精度不低于N2级别
1.7 沉降观测成果整理及计算要求。原始数据要真实可靠,记录计算要符合规范的要求,依据正确,严谨有序,步步校核,结果有效的原则进行成果整理及计算。
2. 具体施测程序及步骤
2.1建立水准控制网。
根据工程的特点布局、现场的环境条件制订测量施测方案,由建设单位提供的水准控制点(或城市精密导线点)根据工程的测量施测方案和布网原则的要求建立水准控制网。要求: (1)一般高层建筑物周围要布置三个以上水准点,水准点的间距不大于100米。
(2)在场区内任何地方架设仪器至少后视到两个水准点,并且场区内各水准点构成闭合图形,以便闭合检校。
(3)各水准点要设在建筑物开挖、地面沉降和震动区范围之外,水准点的埋深要符合二等水准测量的要求(大于1.5米)根据工程特点,建立合理的水准控制网,与基准点联测,平差计算出各水准点的高程。
2.2 建立固定的观测路线。
由场区水准控制网,依据沉降观测点的埋设要求或图纸设计的沉降观测点布点图,确定沉降观测点的位置。在控制点与沉降观测点之间建立固定的观测路线,并在架设仪器站点与转点处作好标记桩,保证各次观测均沿统一路线。
2.3 沉降观测。
根据编制的工程施测方案及确定的观测周期,首次观测应在观测点安稳固后及时进行。一般高层建筑物有一或数层地下结构,首次观测应自基础开始,在基础的纵横轴线上(基础局边)按设计好的位置埋设沉降观测点(临时的),等临时观测点稳固好,进行首次观测。
首次观测的沉降观测点高程值是以后各次观测用以比较的基础,其精度要求非常高,施测时一般用N2或N3级精密水准仪。并且要求每个观测点首次高程应在同期观测两次后决定。
随着结构每升高一层,临时观测点移上一层并进行观测直到十0.00再按规定埋设永久观测点(为便于观测可将永久观测点设于十500mm)。然后每施工一层就复测一次,直至竣工。
2.4 将各次观测记录整理检查无误后,进行平差计算,求出各次每个观测点的高程值。从而确定出沉降量。
某个观测点的每周期沉降量: △c=Hh,I-Hn,I -1 N表示某个观测点,I表示观测周期数(I=1,2,3……)且 H1=H0累计沉降量: △C=∑△ c(n)n表示观测点号。
2.5 统计表汇总
(1)根据各观测周期平差计算的沉降量,列统计表,进行汇总。
(2)绘制各观测点的下沉曲线。
首先建立下沉曲线坐标,横坐标为时间坐标,纵坐标上半部为荷载值,下半部为各沉降观测周期的沉降量。
将统计表中各观测点对应的观测周期所测得沉降量画于坐标中,并将相应的荷载值也画于坐标中,连线,就得到对应于荷载值的沉降曲线。
(3)根据沉降量统计表和沉降曲线图,我们可以预测建筑物的沉降趋势,将建筑物的沉降情况及时的反馈到有关主管部门,正确地指导施工。特别座在沉陷性较大的地基上重要建筑物的不均匀沉降的观测显得更为重要。
利用沉降曲线还可计算出因地基不均匀沉降引起的建筑物倾斜度:q=│△Cm-△Cn│/Lmn,△Cm,△Cn分别为m,n点的总沉降量,Lmn为m,n点的距离。
对沉降观测的成果分析,我们还可以找出同一地区类似结构形式建筑物影响其沉降的主要因素,给施工单位编好施工组织设计正确指导施工大有裨益,同样也为勘察设计单位提供宝贵的一手资料,设计出更完善的施工图纸。
2.6 观测中的注意事项:
(1)严格按测量规范的要求施测。
(2)前后视观测最好用同一水平尺。
(3)各次观测必须按照固定的观测路线进行。
(4)观测时要避免阳光直射,且各观测环境基本一致。
(5)成像清晰、稳定时再读数。
(6)随时观测,随时检核计算,观测时要-气阿成。
(7)在雨季前后要联测,检查水准点的标高是否有变动。
(8)将各次所观测沉降情况及时反馈有关部门,当建筑物每天(24h)连续沉降量超过1mm时应及时的向施工单位和建设单位告知,让施工单位停止施工,会同有关部门采取应急措施。
3.探讨的两个问题
3.1 确定建筑物沉降观测精度的合理性。由于现行规范对施工单位施工过程的沉降观测要求不明朗,这对施工单位在建筑物沉降观测精度选择随意性较大,这就要求检测单位严格把关,提高沉降观测的测量精度,但沉降观测精度选择既不能太高也不能太低,要合理适宜,适合工程特性的需要。既不造成无谓的浪费也要保证观测结果的准确性。这样,本人认为一般高层及重要的建(构)筑物在首次观测过程中适用精密仪器的设备(高级水准仪、铟合金尺等)在±0.00以上部分按二等以上水准测量方法,采用放大率倍数较大的S2或S3水准仪进行观测,也可以测出较理想的结果。
3.2 在沉降观测过程中,沉降量与时问关系曲线不是单边下行光滑曲线,而是起伏状现象。这就分析原因,进行修正。
(1)第二次观测出现回升,而以后各次观测又逐渐下降。可能是首次观测精过低,若回升超过5mm时,第一次观测作废,若回升5mm内,第二次与第一次调整标高一致。 (2)曲线在某点突然回升。
原因:水准点或观测点被碰动所致且水准点碰动后标高低于碰前标高,观测点碰后高于碰前。
处理措施:取相邻另一观测点的相同期间沉降量作为被碰观测点之沉降量。
(3)曲线自某点起渐渐回升。
原因:一般是水准点下沉所致。
措施:确定水准点下沉值,与高级水准点符合测量,确定下沉重。
参考文献
[1] 《工程测量规范》 GB50026-2007.
[2] 《建筑变形测量规范》JGJ8-2007