中国铁物作为中老铁路甲供物资代理服务公司,承担着中老铁路甲供物资采购供应服务、储备基地运营管理、物流配送服务等物资供应保障工作。2017年三季度以来,随着中老铁路施工逐步进入高峰期,钢材等甲供物资面临供应紧张的局面。针对此情况,中国铁物由经营开发部牵头,招标、物流、国际、物贸公司共同参与的中老铁路项目部快速响应,协助老中铁路公司迅速启动2万t钢材应急供应工作,制定了国内钢厂采购方案和从国内港口集港装船,途经泰国港口,再公路转运至老挝的物流组织方案。此次应急供应工作,横跨中、泰、老3国,海洋运输2 500海里,陆路运输约1 400 km,其间克服了钢材价格大幅上涨、钢厂排产困难,泰国港口转运批量大、车辆运输能力不足,老挝正值雨季、道路交通状况差及老挝物资储备基地刚刚建成,装卸设备不足等诸多困难,历时近两个月,目前该批钢材已全部送达中老铁路各施工工区,有效缓解了物资紧张局面,得到了老中铁路公司、各施工单位的高度认可,确保了国家“一带一路”重点项目中老铁路的顺利建设。
China Railway Materials as a middle and old railway A for the agency services, bear the Zhong Lao railway A for the supply of goods procurement services, reserve base operations management, logistics and distribution services and other material supply security work. Since the third quarter of 2017, as the construction of Zhong-Lao Railway has gradually entered a peak period, the supply of such materials as steel products is facing a shortage of supply. In response to this situation, China Railway Materials Co., Ltd., led by the Ministry of Development and Development, responded quickly to the project of Zhong-Lao Railway which took part in the joint bidding, logistics, international trade and logistics companies to assist Lao Zhong-Zhong Railway Company in quickly initiating the emergency supply of 20,000 t steel and formulated Domestic steel mills procurement plan and the logistics organization plan that ships from the domestic port to Hong Kong via the port of Thailand and then to the Lao PDR. The emergency supply work across three countries including China, Thailand and Laos, marine transport of 2,500 nautical miles and overland transport of about 1,400 km, overcame the sharp rise in steel prices, difficulties in steel production scheduling, large transshipment volume of Thai ports, Laos was inundated with rainy seasons, poor traffic conditions and the Laos material reserve base just completed, handling equipment shortage and many other difficulties, which lasted nearly two months, at present the batch of steel has been delivered to all construction work area Zhonglao Railway, effective Alleviating the shortage of materials and getting the high recognition of the Lao ZhongZhong Railway Company and the construction units and ensuring the smooth construction of the Zhong-Lao Railway, a key project of the “Belt and a Road” in the country.