论文部分内容阅读
通过对宣钢8号高炉技术装备和炉型研究分析,结合中钛冶炼原理和高炉炉役中后期炉体维护的实际情况,在入炉钛负荷13.0-15.5kg/t情况下,适时调整高炉操作制度,基本实现了高炉稳定顺行和技术经济指标的持续改善。
Based on the research and analysis of technical equipment and furnace type of No.8 blast furnace in Xuanhua Iron and Steel Co., Ltd., combined with the principle of medium-titanium smelting and the actual condition of furnace maintenance in the middle and later stages of blast furnace operation, under the condition of 13.0-15.5kg / Operating system, the basic realization of the blast furnace stable and technical and economic indicators continue to improve.