分析了地铁站室内环境要求的特殊性,总结了地铁站的空调负荷结构,探讨了空调负荷的变化特性。通过分析地铁站空调系统的设计现状和实际运行情况,指出了其存在的问题,揭示了地铁站过冷现象产生的原因。结合工程实例分析,提出了解决空调系统设备供给能力与负荷需求不匹配问题的方法及节能运行管理措施,并计算了地铁站空调系统的节能潜力。
Analyzes the particularity of indoor environment requirement of subway station, summarizes the air conditioning load structure of subway station, and discusses the changing characteristics of air conditioning load. By analyzing the design status and actual operation status of air-conditioning system in subway station, the existing problems are pointed out and the reasons of subcooling in subway station are revealed. Combining with the engineering case analysis, a method to solve the problem of mismatch of equipment supply capacity and load demand of air-conditioning system and measures of energy-saving operation and management were put forward. Energy-saving potential of air-conditioning system in subway station was calculated.