长沙南站东站房与磁浮站房、东广场、地铁出入口同步施工,与已投入运营的沪昆站房进行无缝对接,周围条件受到很大限制,结合现场情况并综合考虑安全、工期、成本等因素,屋盖钢网架采用分块提升施工技术,利用站台层楼盖作为拼装平台,采用液压同步提升技术,顺利完成了该工程屋盖钢网架结构的安装,为同类型工程施工提供了借鉴。
Changsha South Station East Station room and maglev station room, East Square, the subway entrances and exits simultaneous construction, has been put into operation seamless docking Shanghai and Kunming station, the surrounding conditions are greatly restricted, combined with the scene and considering safety, duration, Cost and other factors, the roof steel grid using block-lifting construction technology, the use of platform floor as a platform assembly floor, using hydraulic synchronous lifting technology, the successful completion of the project roof steel grid structure installation for the same type of construction Provided a reference.