阜新发电厂的建设队伍,发愤图强,自力更生,以三十四天的时间装好了一台大型瓩的汽轮发电机;接着又以六十三天的时间装起了两台大型锅炉的大件,吊装第二台炉的大件只用了一百八十九小时,工期都比以前缩短了一半,并且保证了工程质量。这一经验对于全面完成今年第四季度的电力建设任务,具有重要的意义。这支队伍所以能创造出如此出色的成绩,是不是他们的安装条件好呢?不是的。他们安装的这台机组,比起以前安装的同类型机组来,人力減少三分之户,部分设备、材料也不如以
The construction team at Fuxin Power Station, with its great ambitions and self-reliance, installed a large 瓩 turbine generator in thirty-four days and then installed two large boilers in sixty-three days Large pieces, hoisting the second large furnace only took 189 hours, the construction period is shortened by half than before, and to ensure the quality of the project. This experience is of great significance for the complete fulfillment of the power construction task in the fourth quarter of this year. This team so can create such a good result, is not their installation conditions is good? They installed this unit, compared with the same type of unit previously installed to reduce manpower by one-third, part of the equipment, the material is not as good as