摘要:随着我国社会经济的的不断发展,水利工程行业发展也极为迅速。而冬季施工是水利工程中要面对的一个重大难题,有待相关新技术的改良和各种注意事项的普及。本文主要针对水利工程冬季施工技术存在的问题展开讨论,分析了施工准备工作并提出了一些具体技术手段,对土方工程和混凝土工程列举工程相关注意事项,希望能够对各位同行在水利工程冬季施工方面起到借鉴作用。
关键词:水利工程;冬季施工技术;问题;保障措施
Abstract: With the development of China's economic and social development, development of water conservancy engineering industry is also very quickly. Winter construction is a major problem to face in the water conservancy project, to be the new improved technology and the popularity of various matters needing attention. This paper mainly aimed at the existing winter water conservancy construction technique is discussed, analyzed the construction preparation work and puts forward some concrete techniques, the earthwork and concrete engineering examples and related note, hope to be able to reference for colleagues to play in the water conservancy project winter construction.
Key words: water conservancy project; construction technology in winter; problems; measures
中图分类号:TV5
一、水利工程冬季施工存在的问题
(1)混凝土的水分转移,结构疏散。水分转移、结构疏散的混凝土,表面呈土黄色,冰晶状。这是因为混凝土自身的内部压力和湿度,加之冬季环境下温大差等原因,导致水分由边缘向中心移动,最终造成空隙现象。
(2)混凝土的表面起灰。混凝土表面起灰指的是混凝土粗骨料和砂浆脱离,露出骨料的现象。这个现象产生的原因主要是混凝土混合物中水、灰比太大,离析、泌水情况严重,保水性、聚粘性差,再加之冬季的低温,达不到混凝土的养护温度,水泥水化逐渐停止,接着混凝土的水分迅速蒸发,最后发生了表面起灰现象。
(3)钢筋的锈蚀,混凝土出现裂缝。因为钢筋具有氧化性,氧化锈蚀的同时伴随着体积的膨胀,可能会导致混凝土沿着箍筋或主筋方向产生裂缝;同时,水泥的稳定性不好,失水太快,混凝土的水、灰比太大,早期强度低,都会导致裂缝;混凝土内部水分从边缘移向中心,形成的压力也会引起轴向裂缝。
二、水利工程冬季施工准备工作
(一)进行水利工程冬季施工项目,在入冬之前要拟定冬季施工方案。
方案的基本原则如下:确保质量的原则;经济合理、增加的费用最少的原则;热源和材料有可靠来源,尽量减少消耗的原则。
方案的基本内容包括:施工程序;施工方法;现场布置;设备、材料、能源、工具的供应计划;安全防火措施;测温制度和质量检查制度等。
(二)反复审核、校验施工图纸,检查其是否能够符合冬季施工要求。
(三)在进入冬季施工前,要组织相关部门人员进行专门的技术培训,明确个人和团队的职责,在考试合格之后才可以上岗工作。
(四)安排固定专业人员对冬季施工期的室、内外气温以及砂桨、混凝土等材料进行测温并及时做好记录工作。
(五)及时与当地气象站联系并接收天气预报,以防止寒流突袭,在不利于施工的天气到来之前做好应对准备。
(六)现场准备。
1.根据工程量所需,提前组织相关工具、器械、材料进场。
2.检查设备的安全可靠性。
3.计算变压器容量,接通电源。
4.做好临时管道和白灰膏等的防冻工作。
5.做好冬季混凝土、摻外加剂和砂浆的适配工作。
(七)安全与防火。
1.冬期施工时,要采取防滑措施。
2.大雪过后要立即清扫积雪,检查基础设施,及时处理松动、下沉现象。
3.施工时如接触汽源、热水,要防止烫伤;使用氯化钙、漂白粉时,要防止腐蚀皮肤。
4.严加保管亚硝酸钠等有毒物品。
5.现场火源,要加强管理;使用天然气、煤气时,要注意方法,防止爆炸;并注意及时通风换气,防止中毒。
6.电源、控制箱等设备要加保险箱、锁,并安排专人管理,防止漏电或触电情况的发生。
三、水利工程冬季施工的具体技术保障
以土方工程和混凝土工程为例解释有关水利工程具体的冬季施工技术,列举了一些在施工过程中应当注意的重点问题。
(一)土方工程
1.土方开挖在冬期机械施工时,其施工方法应按防火冻结法进行。
2.用防火冻结法进行土方的开挖时,在冻结之前要将表面土翻耕,翻耕深度根据具体气温确定,一般不小于0. 3m。
3.在开挖基坑和管沟时,要防止基土受冻。应在基底标高以上预留适当厚度的松土。
4.要经过经济比较后确定施工方法,再进行填方工程的施工。
5.冬期填方前,应去除基底上的保温材料和冰雪,在距离边坡表层1m以内处不得用冻土填筑。
6.室外平均气温在零下5℃以上时,冬季施工填方高度不受温度限制;平均温度在-5℃以下时,填方高度不宜超过规定。
7.冬季回填土方,铺筑的厚度要比常温下施工时减小百分之二十至百分之二十五,冻土块的体积不能超过填方总体积的百分之十五;其粒径不得大于150mm。铺冻土块时切记要均匀分布,逐层夯实。回填土方的工作不可间断,并且在回填土方的同时要采取防冻措施。
8.成品保护
①施工时,对轴线控制桩、定位标准桩、标准水准点以及龙门板等,填运土方的过程巾不得碰撞。并应定期复测检查这些标准桩点是否正确。
②夜间施工时,合理安排工序,施工前要布置好足够的照明设备。防止铺填过厚,禁止直接用汽车将土倒人基槽内。但大型地坪不受限制。
③现浇混凝土要达到一定强度,不至于因为回填土而受到破坏。
(二)混凝土工程
冬季,混凝土工程的施工要从其工程特点出发,选择恰当的施工措施。
1.如果新浇筑的混凝土受冻,拌合水冻结,就会导致体积增加,同时水泥的水化作用停止进行。在恢复正常温度养护以后,水泥浆体中的孔隙率明显增加,导致了混凝土的各项性能下降。因此在浇筑混凝土的时候要做好混凝土的保温工作。
2.混凝土的温度降至O℃前,其抗压强度不得低于抗冻临界强度。
抗冻临界强度规定如下:(1)硅酸盐水泥配制的混凝土,为设计的混凝土强度标准值的百分之三十;(2)矿渣硅酸盐水泥配制的混凝土,为设计的混凝土强度标准值的百分之四十,但Cl0及Cl0以下等级的混凝土,不得低于5.ON/mm2。
3.冬季施工的混凝土一般应选用普通硅酸盐水泥,这样使为了缩短养护时间,水泥的强度等级不宜低于42.5,每立方米混凝土中的水泥用量最好高于300kg,水灰比不应大于0.60,并加入早强剂。
4.为了减少冻害,应控制坍落度,加入减水剂,优先选用高效减水剂。
5.为了防止钢筋的锈蚀,在钢筋混凝土中,氯盐掺量不能超过水泥重量的1%,掺氯盐的混凝土必须振捣密实。
在下列情况或结构中,不能在钢筋混凝土中掺人氯盐:
(1)空气湿度高的环境中;(2)赴于水位升降部位的结构;(3)露天或经常受水淋的结构;(4)铝铁相接触部,镀锌结构,以及外露钢筋部位等一些可能发生腐蚀却无保护措施的部位;(5)与含有酸、碱等侵蚀性介质相接触的结构;(6)长期在60℃环境下使用的结构;(7)使用冷拉钢筋或冷拔低碳钢丝的结构;(8)薄壁结构,中、重级吊车梁,屋架等结构;(9)电解车间和直接靠近直流电源的结构;(10)直接靠近高压电源的结构。
6.为了不影响混凝土的美观,并防止其对人体健康产生危害,混凝土中尿素掺量不能超过水泥重量的4%。
四、结束语
水利工程由于自身工程周期较长、工程量较大的特点,必然会遇到在冬季施工的情况。冬季施工是水利工程中要面对的一个重大难题,我国气候复杂,尤其在北方高寒地区,冬季施工受工期、天气等因素的制约,存在很多有待解决的问题。水利工程冬季施工人员必须以严谨的态度对待每一次的施工,严格按照各项指标执行方案,对自己的工作负责,对工程负责,与全体人员一起建造出质量第一的工程项目。
参考文献:
1 李春荣;殷一华;;浅谈冬季施工防冻剂的应用[J];中小企业管理与科技(上旬刊);2010年10期
2 宁亚瑜;;浅谈混凝土冬季施工的质量控制及技术措施[J];现代物业(中旬刊);2010年03期
3 张朝阳;;冬季渠道混凝土施工措施及热工计算[J];宁夏农林科技;2008年06期
4 高俊山;;冬季施工混凝土浇筑注意事项[J];黑龙江科技信息;2009年29期
5 张辉;张驰;徐亮;郭梦法;;浅谈水利工程施工技术[J];中国水能及电气化;2010年12期
关键词:水利工程;冬季施工技术;问题;保障措施
Abstract: With the development of China's economic and social development, development of water conservancy engineering industry is also very quickly. Winter construction is a major problem to face in the water conservancy project, to be the new improved technology and the popularity of various matters needing attention. This paper mainly aimed at the existing winter water conservancy construction technique is discussed, analyzed the construction preparation work and puts forward some concrete techniques, the earthwork and concrete engineering examples and related note, hope to be able to reference for colleagues to play in the water conservancy project winter construction.
Key words: water conservancy project; construction technology in winter; problems; measures
中图分类号:TV5
一、水利工程冬季施工存在的问题
(1)混凝土的水分转移,结构疏散。水分转移、结构疏散的混凝土,表面呈土黄色,冰晶状。这是因为混凝土自身的内部压力和湿度,加之冬季环境下温大差等原因,导致水分由边缘向中心移动,最终造成空隙现象。
(2)混凝土的表面起灰。混凝土表面起灰指的是混凝土粗骨料和砂浆脱离,露出骨料的现象。这个现象产生的原因主要是混凝土混合物中水、灰比太大,离析、泌水情况严重,保水性、聚粘性差,再加之冬季的低温,达不到混凝土的养护温度,水泥水化逐渐停止,接着混凝土的水分迅速蒸发,最后发生了表面起灰现象。
(3)钢筋的锈蚀,混凝土出现裂缝。因为钢筋具有氧化性,氧化锈蚀的同时伴随着体积的膨胀,可能会导致混凝土沿着箍筋或主筋方向产生裂缝;同时,水泥的稳定性不好,失水太快,混凝土的水、灰比太大,早期强度低,都会导致裂缝;混凝土内部水分从边缘移向中心,形成的压力也会引起轴向裂缝。
二、水利工程冬季施工准备工作
(一)进行水利工程冬季施工项目,在入冬之前要拟定冬季施工方案。
方案的基本原则如下:确保质量的原则;经济合理、增加的费用最少的原则;热源和材料有可靠来源,尽量减少消耗的原则。
方案的基本内容包括:施工程序;施工方法;现场布置;设备、材料、能源、工具的供应计划;安全防火措施;测温制度和质量检查制度等。
(二)反复审核、校验施工图纸,检查其是否能够符合冬季施工要求。
(三)在进入冬季施工前,要组织相关部门人员进行专门的技术培训,明确个人和团队的职责,在考试合格之后才可以上岗工作。
(四)安排固定专业人员对冬季施工期的室、内外气温以及砂桨、混凝土等材料进行测温并及时做好记录工作。
(五)及时与当地气象站联系并接收天气预报,以防止寒流突袭,在不利于施工的天气到来之前做好应对准备。
(六)现场准备。
1.根据工程量所需,提前组织相关工具、器械、材料进场。
2.检查设备的安全可靠性。
3.计算变压器容量,接通电源。
4.做好临时管道和白灰膏等的防冻工作。
5.做好冬季混凝土、摻外加剂和砂浆的适配工作。
(七)安全与防火。
1.冬期施工时,要采取防滑措施。
2.大雪过后要立即清扫积雪,检查基础设施,及时处理松动、下沉现象。
3.施工时如接触汽源、热水,要防止烫伤;使用氯化钙、漂白粉时,要防止腐蚀皮肤。
4.严加保管亚硝酸钠等有毒物品。
5.现场火源,要加强管理;使用天然气、煤气时,要注意方法,防止爆炸;并注意及时通风换气,防止中毒。
6.电源、控制箱等设备要加保险箱、锁,并安排专人管理,防止漏电或触电情况的发生。
三、水利工程冬季施工的具体技术保障
以土方工程和混凝土工程为例解释有关水利工程具体的冬季施工技术,列举了一些在施工过程中应当注意的重点问题。
(一)土方工程
1.土方开挖在冬期机械施工时,其施工方法应按防火冻结法进行。
2.用防火冻结法进行土方的开挖时,在冻结之前要将表面土翻耕,翻耕深度根据具体气温确定,一般不小于0. 3m。
3.在开挖基坑和管沟时,要防止基土受冻。应在基底标高以上预留适当厚度的松土。
4.要经过经济比较后确定施工方法,再进行填方工程的施工。
5.冬期填方前,应去除基底上的保温材料和冰雪,在距离边坡表层1m以内处不得用冻土填筑。
6.室外平均气温在零下5℃以上时,冬季施工填方高度不受温度限制;平均温度在-5℃以下时,填方高度不宜超过规定。
7.冬季回填土方,铺筑的厚度要比常温下施工时减小百分之二十至百分之二十五,冻土块的体积不能超过填方总体积的百分之十五;其粒径不得大于150mm。铺冻土块时切记要均匀分布,逐层夯实。回填土方的工作不可间断,并且在回填土方的同时要采取防冻措施。
8.成品保护
①施工时,对轴线控制桩、定位标准桩、标准水准点以及龙门板等,填运土方的过程巾不得碰撞。并应定期复测检查这些标准桩点是否正确。
②夜间施工时,合理安排工序,施工前要布置好足够的照明设备。防止铺填过厚,禁止直接用汽车将土倒人基槽内。但大型地坪不受限制。
③现浇混凝土要达到一定强度,不至于因为回填土而受到破坏。
(二)混凝土工程
冬季,混凝土工程的施工要从其工程特点出发,选择恰当的施工措施。
1.如果新浇筑的混凝土受冻,拌合水冻结,就会导致体积增加,同时水泥的水化作用停止进行。在恢复正常温度养护以后,水泥浆体中的孔隙率明显增加,导致了混凝土的各项性能下降。因此在浇筑混凝土的时候要做好混凝土的保温工作。
2.混凝土的温度降至O℃前,其抗压强度不得低于抗冻临界强度。
抗冻临界强度规定如下:(1)硅酸盐水泥配制的混凝土,为设计的混凝土强度标准值的百分之三十;(2)矿渣硅酸盐水泥配制的混凝土,为设计的混凝土强度标准值的百分之四十,但Cl0及Cl0以下等级的混凝土,不得低于5.ON/mm2。
3.冬季施工的混凝土一般应选用普通硅酸盐水泥,这样使为了缩短养护时间,水泥的强度等级不宜低于42.5,每立方米混凝土中的水泥用量最好高于300kg,水灰比不应大于0.60,并加入早强剂。
4.为了减少冻害,应控制坍落度,加入减水剂,优先选用高效减水剂。
5.为了防止钢筋的锈蚀,在钢筋混凝土中,氯盐掺量不能超过水泥重量的1%,掺氯盐的混凝土必须振捣密实。
在下列情况或结构中,不能在钢筋混凝土中掺人氯盐:
(1)空气湿度高的环境中;(2)赴于水位升降部位的结构;(3)露天或经常受水淋的结构;(4)铝铁相接触部,镀锌结构,以及外露钢筋部位等一些可能发生腐蚀却无保护措施的部位;(5)与含有酸、碱等侵蚀性介质相接触的结构;(6)长期在60℃环境下使用的结构;(7)使用冷拉钢筋或冷拔低碳钢丝的结构;(8)薄壁结构,中、重级吊车梁,屋架等结构;(9)电解车间和直接靠近直流电源的结构;(10)直接靠近高压电源的结构。
6.为了不影响混凝土的美观,并防止其对人体健康产生危害,混凝土中尿素掺量不能超过水泥重量的4%。
四、结束语
水利工程由于自身工程周期较长、工程量较大的特点,必然会遇到在冬季施工的情况。冬季施工是水利工程中要面对的一个重大难题,我国气候复杂,尤其在北方高寒地区,冬季施工受工期、天气等因素的制约,存在很多有待解决的问题。水利工程冬季施工人员必须以严谨的态度对待每一次的施工,严格按照各项指标执行方案,对自己的工作负责,对工程负责,与全体人员一起建造出质量第一的工程项目。
参考文献:
1 李春荣;殷一华;;浅谈冬季施工防冻剂的应用[J];中小企业管理与科技(上旬刊);2010年10期
2 宁亚瑜;;浅谈混凝土冬季施工的质量控制及技术措施[J];现代物业(中旬刊);2010年03期
3 张朝阳;;冬季渠道混凝土施工措施及热工计算[J];宁夏农林科技;2008年06期
4 高俊山;;冬季施工混凝土浇筑注意事项[J];黑龙江科技信息;2009年29期
5 张辉;张驰;徐亮;郭梦法;;浅谈水利工程施工技术[J];中国水能及电气化;2010年12期