“七五”期间辽河油田建成一次变电所60kV出口4个,建成并投产60kV/6kV变电所18座,扩建变电所4座。新增设备容量171800kVA。为满足上产用电,还建设临时变电所9座。完成自备电厂新增装机容量85200kW的扩建主体工程。建成60kV送电线路20条,计382km。完成6kV配电线路近千公里。累计完成供电量524935kW·h。新增固定资产近亿元。“八五”期间,辽河油田的电力工程建设将
During the “Seventh Five-Year” period, Liaohe Oilfield completed a substation 60kV export 4, built and put into operation 18kV substations 60kV / 6kV, expansion substations 4. New equipment capacity 171800kVA. To meet the electricity production, but also to build temporary substation 9. Completion of self-provided power plant new installed capacity of 85200kW expansion of the main project. Built 60kV transmission lines 20, total 382km. Complete 6kV distribution lines nearly a thousand kilometers. Accumulated power supply 524935kW · h. New fixed assets of nearly 100 million yuan. During the “Eighth Five-Year Plan” period, construction of Liaohe Oilfield will be completed