现代化的7米大采高综采工作面设备安装具有吨位大,体积大等特点,其安装质量的优劣直接制约着综采工作面的回采速度和产能的发挥,文章以红柳林矿业公司的25202综采工作面设备安装为例,介绍了大功率无轨胶轮车和平行作业法在7米大采高设备安装工程中的应用和革新,不仅节约了安装工期,而且优化了施工方案,系统而科学地总结了该工艺方案。
The installation of modern 7m mining height fully mechanized coal mining face has the features of large tonnage and large volume. The quality of its installation directly restricts the recovery rate and productivity of fully mechanized coal mining face. The paper takes Hongliulin Mining Company 25202, this paper introduces the application and innovation of high-power railless rubber tire truck and parallel operation method in the installation of 7m high mining equipment, which not only saves the installation period, but also optimizes the construction scheme and system Scientifically summed up the process.