山东河务局金堤修防段,去年试做了抽水窨堤工程,效果很好。在1,005公尺的堤段上,发现隐患125处,最大洞穴填土328.63方。为进一步加固堤防,清查和消减隐患,提供了一种新的方法。一、施工过程与效果抽水窨堤工程是分四期进行的。施工前进行了工地勘测工作,对于水源、堤身土质、大堤断面以及抽水机的安装位置均进行了调查与了解,并准备了必须的器材。
Shandong Provincial Bureau Jindi repair section last year tried pumping pumping embankment project, the effect is very good. On the embankment section of 1,005 meters, 125 hidden dangers were found and the largest cave was filled with 328.63 square meters. To further reinforce the embankment, inventory and reduce hidden dangers, provides a new method. First, the construction process and results Pumping embankment project is carried out in four phases. Prior to construction, the site investigation was carried out. The water source, the embankment soil, the section of the embankment and the installation position of the water pump were investigated and understood, and the necessary equipment was prepared.