凌津滩水电站装机9台,共270MW。工程1994年开工,1998年底第一台机组发电,2001年工程完工。1992年。国家计委批准的工程动态总投资为32.50亿元(当时装机8台240/MW);1995年可行性研究静态投资为20.03亿元,动态投资为33.11亿元,其中利用亚行贷款1.16亿美元,配套内资23亿元;1997年增加一台30MW 机组,新增投资9 740万元(其中外资619万美元,配套内资4582万元)。建设中实行业主责任制、招投标制、建设监理和设计优化,实际发生的投资没有超过初步设计概算,比国家批准的预期投资节约3.5亿元;实际发电工期提前了10个月,在工程管理、投资控制、质量保证等方面,取得了令人满意的成绩。
Lingjin Hydropower Station installed 9 units, a total of 270MW. The project started in 1994, the first generating unit by the end of 1998, completed in 2001. 1992. The total project dynamic investment approved by the State Development Planning Commission was 3.25 billion yuan (8 240 / MW installed at that time); in 1995, the static investment in the feasibility study was 2.003 billion yuan and the dynamic investment was 3,311 million yuan, of which the loan from the ADB was 116 million U.S. dollars With an investment of 2.3 billion yuan. In 1997, an additional 30MW unit was added, with an additional investment of 97.4 million yuan (of which foreign capital was 6,190,000 U.S. dollars and domestic capital was 45.82 million yuan). The implementation of the owners responsibility system, bidding system, construction supervision and design optimization, the actual investment did not exceed the preliminary design estimates than the state approved the expected investment savings of 350 million yuan; the actual power generation period 10 months ahead of schedule, project management , Investment control, quality assurance and other aspects, has achieved satisfactory results.