论文部分内容阅读
介绍了五强溪水电厂厂房2台起重桥机电控系统改造项目情况,重点阐述了1号机组A级检修过程中,利用厂房2台桥机并车操作起吊发电机转子,桥机出现严重异常情况的分析处理,以供探讨和交流学习。
Introduced the Wuqiangxi Hydropower Plant 2 sets of lifting bridge mechanical and electrical control system renovation project, focusing on the No. 1 Unit A-class maintenance process, the use of plant 2 bridge machine and car operation generator rotor, the bridge machine serious Analysis of abnormal conditions for discussion and exchange of learning.