针对多模式资源受限项目调度中的干扰管理仿真研究较少这一现状,分析了MS Project项目管理工具的功能弱项,借助CPLEX Studio IDE的优化计算功能,设计了较为合理的干扰管理仿真流程,实现了多模式资源受限项目调度中的干扰管理仿真。分析了单一时刻单一干扰和多个时刻多个干扰的情况,并基于项目调度问题库的实例进行仿真,结果表明,资源冲突对项目调度的工期偏移量影响作用较大,设计的仿真流程具有一定的有效性,可为武器装备项目的管理人员进行计划、决策等工作提供参考和借鉴。
In view of the fact that there are few research on the simulation of interference management in the multi-mode resource-limited project scheduling, this paper analyzes the function weakness of the MS Project project management tool. With the help of CPLEX Studio IDE’s optimization calculation function, a more reasonable interference management simulation process is designed, The simulation of interference management in multi-mode resource limited project scheduling is realized. The single disturbance at one time and multiple disturbances at multiple time points are analyzed. Based on the example of the project scheduling problem library, the simulation results show that the resource conflict has a great effect on the project schedule offset and the simulation flow has A certain degree of effectiveness can provide reference and reference for the management of weapons and equipment project planning, decision-making and other work.