我单位在中日友好医院楼梯扶手安装中,采用了化学锚固螺栓法。安装工序如下:外墙饰面甩一道涂料,弹线,确定螺栓孔位置,钻孔,孔径为φ18毫米,清理、安装锚固螺栓,自然养护18小时,孔口捻灰,安装扶手连接件,扶手就位固定及伸缩缝处理,做外墙交活涂料,施工完毕。这种锚固方法,钻孔要求较深,锚固时间间隔较长,当螺栓装入后,口部四周需捻灰或抹灰找平。见图1。
In the installation of staircase handrails in China-Japan Friendship Hospital, our company adopted the chemical anchor bolt method. The installation procedure is as follows: throw a paint on the outer wall finish, strike the wire, determine the position of the bolt hole, drill holes, drill hole diameter φ18mm, clean and install the anchor bolt, naturally maintain for 18 hours, put the dust on the hole, install the handrail connector, handrail In-place fixed and expansion joint processing, do exterior wall paint, construction is completed. This kind of anchoring method requires deeper drilling and longer anchoring time intervals. After the bolts are installed, it is necessary to level the ash or plaster around the mouth. see picture 1.