为了加快工程进度,节约投资,灵宝市白虎潭水库大坝施工时,采用了碾压混凝土通仓薄层施工工法,简化施工程序、提高机械化程度、水泥用量小,粉煤灰用量大,节能环保。通过钻孔取芯,芯样胶结较好、骨料分布均匀,未见单层碾压层内有断裂。抗压、抗渗强度均达到设计的要求。2016年5月19日大坝开始下闸蓄水,通过各种观测数据分析,水库大坝的稳定、强度、防渗等指标达到了设计要求,水库运行正常。该工程提前30 d完成,施工过程中基本未采取温控措施,节省工程投资100万元。
In order to speed up the progress of the project and save investment, the construction of the Baihutan Reservoir Dam in Lingbao City adopted a thin layer construction method of RCC construction to simplify construction procedures, improve mechanization, use less cement, large amount of fly ash and save energy Environmental protection. Coring by drilling, core-like cement better, uniform aggregate distribution, no single-layer cracks within the laminated layer. Compressive and impervious strength meet the design requirements. On May 19, 2016, the dam started to shut down for water storage. Through various observation data analysis, the stability, strength and seepage prevention of the dam met the design requirements and the reservoir operated normally. The project completed 30 days in advance, the basic temperature control measures are not taken during the construction process, saving 100 million yuan project investment.