帆布在大治河东闸维修工程围堰中的应用

来源 :上海水利 | 被引量 : 0次 | 上传用户:bjzcha
下载到本地 , 更方便阅读
声明 : 本文档内容版权归属内容提供方 , 如果您对本文有版权争议 , 可与客服联系进行内容授权或下架
论文部分内容阅读
大治河东闸闸外排水河开通与水闸维修工程是我市1992年重点水利建设项目。该工程施工中采用了防雨帆布作防渗围堰,自1992年6月26日抽水至12月21日水闸维修工程结束,围堰挡水时间长达五个月,安渡了一个汛期,保证了水闸维修工程的顺利进行。大治河东闸始建于1978年。由于不均匀沉降等原因导致水闸结构发生较严重的损坏,又由于闸外排水河未开通,因此,建闸十多年未投入运行。为使水闸尽早发挥效益,市计委于1991年落实了水闸维修费用,并由第 Dazhi He Dong gate outside the drainage river opened with sluice maintenance project is the city’s major water conservancy construction project in 1992. The project uses a rain-proof canvas impermeable cofferdam, pumping from June 26, 1992 to December 21, sluice repair work is completed, the cofferdam water for up to five months, Ante had a flood season, to ensure that The sluice maintenance works smoothly. Dazhi East Gate was built in 1978. Due to uneven settlement and other causes of sluice structure more serious damage, but also due to the gate outside the drainage river is not open, therefore, built gate for more than 10 years has not been put into operation. In order to bring the floodgates into effective as early as possible, the municipal planning commission implemented the sluice maintenance costs in 1991,
其他文献
1 提要随着 2 0 0 1年西澳大利亚MBWAMarbeBar台站的完成和加那利群岛Taburiente台站的关闭 ,美国地震学合作研究会全球地震台网共有 1 2 5个台站。全球地震台网包含 72个美
《人民长江》创刊40年的回顾《人民长江》编辑部《人民长江》杂志自1955年8月创刊,现已40年。《人民长江》杂志自创刊以来,始终坚持“宣传治理开发长江的方针和政策,报导国内外水利水电先
三峡工程施工正点运行略有提前长江三峡工程自1994年12月14日正式开工以来,目前正按国务院批准的施工网络计划正点运行,略有提前。几个主要工程项目的施工进度都在提前。如无特大自然灾
长江三峡工程正式开工1994年12月14日,长江三峡工程开工典礼在湖北宜昌三斗坪举行。江流滚滚,彩旗飞扬。主会场上"长江三峡工程开工典礼"十个金光大字显得格外引人注目。开工典礼隆重而简
电力拖动是职业技术学校机电一体化专业的课程,具有较强的应用性与实践性。在现代的生产中,运用到电力拖动的区域依然非常广泛。在进行电力拖动的教学中,传统的教学方法虽然
2015年10月22日,中国音乐学院国音堂音乐厅迎来了一场特别演出,观众们对此充满了期待,因为这是北京京剧院新近推出的一部具有实验创新的小剧场京剧——《馒头山》。此次演出
军事题材纪录片以军事活动、军事人物或军事任务为记录对象,具有独特的表现主题、拍摄领域和表现方式,是电视纪录片的重要组成部分。长期以来,军事题材纪录片伴随人民军队的
相对于传统德育而言,“体验式”德育是一种快乐的教学,不是空洞的说教、灌输,它的核心在于让学生亲身参与到德育过程中,从过程中获得品格和道德观的升华,使学生入脑入心,产生