5月份,吉林石化公司将迎来三年一次的装置停车大检修,动力二厂——专门负责水电汽能源供应的自备电厂——也将乘此空窗期进行设备升级改造和系统消缺。与其他停车检修单位不同的是,该厂要最后停车、最早启动,要在11天的时间里完成124个检修项目,而且还要保证检修后一次开车成功,向西部丙烯腈、ABS、合成氨等化工装置输送能源,保证其检修后开车用汽需求。当“安全第一”的指令从公司发出后,该厂从上到下,开始紧锣密鼓落
In May, Jilin Petrochemical Company will usher in a three-year installation and overhaul of power plants. Power Plant 2, a self-provided power plant that is responsible for the supply of hydropower and steam energy, will also take this opportunity to upgrade and eliminate equipment . The difference is that with the other parking maintenance unit, the plant to the last stop, the earliest start, to be completed in 11 days time 124 maintenance projects, but also to ensure that after a successful car maintenance, to the west of acrylonitrile, ABS, ammonia, etc. Chemical plant transportation of energy to ensure that after its overhaul car steam demand. When the “safety first ” command issued from the company, the plant from top to bottom, began intense