1 左岸大坝 左岸非溢流坝段混凝土1996年开始浇筑施工,目前左非坝段除11号、13号外,其余非溢流坝段全部已达坝顶设计高程。左岸厂房坝段及河床泄洪坝段,1997年末至1999年一季度陆续完成基础开挖并开始混凝土工程施工。目前,泄洪坝段2个坝段混凝土浇筑已达坝顶,其余坝段最低已达高程152m;左导墙坝段浇筑至高程157m;左厂1号至6号坝段混凝土已达坝顶,左厂其他坝段最低高程达142m。
1 left bank dam left bank non-overflow dam concrete began pouring construction in 1996, the current non-left dam section No. 11, No. 13, the remaining non-overflow dam section has reached the design elevation of the dam. The left bank of the plant dam section and the flood discharge dam section of the riverbed, from late 1997 to the first quarter of 1999 to complete the foundation excavation and start concrete construction. At present, the concrete pouring of the two dam sections of the flood discharge dam section has reached the top of the dam, and the minimum of the remaining dam sections has reached the elevation of 152m; the left guide wall dam section is poured to an elevation of 157m; the concrete of the dam sections No.1 to No.6 in the left factory has reached the dam crest, The left dam other dam minimum elevation of 142m.