我国煤矿使用钻井法凿井中,多数井筒以钻进表土层为主。随着专用钻机性能的提高,钻进井筒将向全深深井发展,淮北童亭主井设计钻进600米井筒全深,但在井壁支护方法上仍采用在洗井液中漂浮下沉的方法(见“建井技术”1983年第1期)。虽然这种方法简单,施工质量好,而对深井,特别是下半部是基岩时,由于施工载荷大,造成基岩部分井壁很厚,技术上和经济上都将是不够合理的。本文拟对深井钻井的井壁结构和施工方法的改进提一些探讨性意见。
Drilling wells drilled in China’s coal mine, the majority of the wellbore to the topsoil. With the improvement of the performance of special drilling rigs, the borehole borehole will develop into a fully deep borehole. The main shaft of Tongting, Huaibei has been drilled to a full depth of 600 meters. However, the wellbore support method is still floating and sinking Method (see “Well Construction Technology” 1983 the first period). Although this method is simple and the construction quality is good, it is not technically and economically reasonable for deep wells, especially the lower half, to be bedrock due to the large construction load, resulting in thick wall sections of the bedrock. This article intends to put forward some exploration opinions on the improvement of the shaft wall structure and construction method of deep well drilling.