电力工业部水电工程造价管理考察团于1994年赴美国、加拿大考察了哈扎公司、田纳西流域管理局、美国造价工程师协会、魁北克水电公司、安大略水电公司等单位。考察团了解了这两个国家的水电项目建设程序、水电开发阶段划分、工程量计算规则、总概算构成、各设计阶段确定造价的方法和相应的允许偏差幅度、人工工资构成、不可预见费的内容和费率、资金流编制、通货膨胀率的取用、施工阶段的造价控制等问题。在此基础上,对我国水电的发展和改革提出了几点看法和建议。
Ministry of Electric Power Industry, the cost of hydropower project management delegation to the United States in 1994, Canada inspected the Hazza company, the Tennessee Valley Authority, the United States Association of cost engineers, the Quebec Hydro, Ontario Hydroelectric Corporation and other units. The delegation learned about the hydropower project construction procedures, hydropower development phase allocation, construction quantity calculation rules and total budget estimates in each of the two countries, the method of determining the cost in each design phase and the corresponding allowable deviations, the composition of artificial salaries, the unforeseen costs Content and rates, cash flow preparation, access to inflation rates, the construction phase of the cost control and other issues. On this basis, some suggestions and suggestions on hydropower development and reform in our country are put forward.