北京市第二建筑公司四工程处一工地担负的529电站扩建工程,自去年年末开工以来直到今年四月初,由于材料严重不足和技术资料的影响,一直处在半停半打的状态。但在市委和公司党委的直接领导下,这个工地坚持了政治挂帅,大搞群众运动,千方百计克服材料不足的困难,上半年不但超额完成了工作量计划,更重要的是胜利地完成了一台汽轮发电机“七一”发电的土建工程项目。这项工程是在材料、图纸、机械不足的情况下,采用边准备、边施工的方法开工的。开工后,材料、图纸仍然不能满足需要,有了作这个基础的材料,没有作那个基础的材料,有了这个图纸,没有那个图纸,有的有了材料和图纸,又没有吊装机具。这时候,各种右倾保守的论调就出来了。有的干部说:“材料没有,为什么要开工呢,这开工和
The construction of the 529 power station expansion project undertaken by the Beijing Second Construction Company 4 Engineering Office at a construction site has been in a state of half-a-half dormant since the beginning of last year and the beginning of April this year due to material shortage and technical data. However, under the direct leadership of the municipal party committee and the company’s party committee, the construction site has insisted on political incumbency and vigorously engaged in mass movements, and has done everything possible to overcome the difficulties of lack of materials. In the first half of the year, it not only overworked its workload plan, but more importantly it successfully completed one. Turbine Generator ”Single“ Power Generation Civil Engineering Project. This project started with the methods of preparation and construction in the absence of materials, drawings, and machinery. After the start of construction, the materials and drawings still cannot meet the needs. With the materials used as the basis, there are no materials for that foundation. With this drawing, there are no drawings, some have materials and drawings, and there are no hoisting equipment. At this time, various right-conservative conservative arguments came out. Some cadres said: ”The material is not. Why should we start work? This starts with